ANNEX A
AN OUTLINE PLAN AND TIMETABLE FOR RE-LOCATING BY 31 MARCH 1979 IN HE'S TAMAR AND ELSEWHERE THE FUTURE HEADQUARTERS BRITISH FORCES HONG KONG AND ALL THOSE SUFFORTING ELEMENTS WHICH ARE NOW STATIONED IN VICTORIA BARRACKS
INTRODUCTION
1.
Terms of Reference
2.
8.. To submit by 21 November to the Working Party an Outline Flan and a time- table for relocating by 31 March 1979 in HMS TAMAR (and elsewhere if necessary) the future HQ British Forces, Hong Kong, and all those supporting elements which are now stationed in Victoria Barracks.
b.
To estimate the total cost of such reprovisioning at September 1975 prices.
Composition of Victoria Sub-Committee
Deputy Commander Land Forces
Captain-in-Charge Hong Kong
Colonel GS HQ Land Forces
Regional Director PSA
Secretary for Security
Chairman
Principal Government Architect
3.
Secretary to CAPIC Hong Kong
GS02 (SD) HQ Land Forces
Planning Assumptions.
E
Joint Secretaries
The sub-committee made the following planning assumptions:
Maintenance of Operations in HMS TAMAR. Continuous operation and support of the Hong Kong Squadron and Service Water Transport from HMS TAMAR is to be maintained throughout the whole period.
b.
Land Area. It will not be acceptable to Hong Kong Government for any in- crease to be made to the area now occupied by HMS TAMAR. However, improved ac- cess to the Central District road system will be necessary.
c.
Deep Water Berths. New construction within the perimeter of HS TAMAR is not to prejudice the alongside deep water berthing facilities currently avail- able for the use of visiting ships.
a.
Building.
Planning should not preclude:
(1) Knocking down what is old and outdated in HMS TAMAR or moving what is
now in Tamar elsewhere.
A - 1