ANNEX A

AN OUTLINE PLAN AND TIMETABLE FOR RE-LOCATING BY 31 MARCH 1979 IN HE'S TAMAR AND ELSEWHERE THE FUTURE HEADQUARTERS BRITISH FORCES HONG KONG AND ALL THOSE SUFFORTING ELEMENTS WHICH ARE NOW STATIONED IN VICTORIA BARRACKS

INTRODUCTION

1.

Terms of Reference

2.

8.. To submit by 21 November to the Working Party an Outline Flan and a time- table for relocating by 31 March 1979 in HMS TAMAR (and elsewhere if necessary) the future HQ British Forces, Hong Kong, and all those supporting elements which are now stationed in Victoria Barracks.

b.

To estimate the total cost of such reprovisioning at September 1975 prices.

Composition of Victoria Sub-Committee

Deputy Commander Land Forces

Captain-in-Charge Hong Kong

Colonel GS HQ Land Forces

Regional Director PSA

Secretary for Security

Chairman

Principal Government Architect

3.

Secretary to CAPIC Hong Kong

GS02 (SD) HQ Land Forces

Planning Assumptions.

E

Joint Secretaries

The sub-committee made the following planning assumptions:

Maintenance of Operations in HMS TAMAR. Continuous operation and support of the Hong Kong Squadron and Service Water Transport from HMS TAMAR is to be maintained throughout the whole period.

b.

Land Area. It will not be acceptable to Hong Kong Government for any in- crease to be made to the area now occupied by HMS TAMAR. However, improved ac- cess to the Central District road system will be necessary.

c.

Deep Water Berths. New construction within the perimeter of HS TAMAR is not to prejudice the alongside deep water berthing facilities currently avail- able for the use of visiting ships.

a.

Building.

Planning should not preclude:

(1) Knocking down what is old and outdated in HMS TAMAR or moving what is

now in Tamar elsewhere.

A - 1

CONFIDENTIAL,