A (2) 25

Hon. C. T.

I do not understand this. The contract was signed on 7/3/29 to be completed within 6 months (vide D.P.W's. minute of 18.3.29 above). In his minute of 5.2.31 the D.P.W. states that the date due for completion was 7/9/30 and calculates the fine on this basis.

Surely there is a mistake somewhere of one whole year.

I do not think the security should be released until this point is cleared up.

(Sgd.) P. L. COLLISSON,

Auditor.

21.2.31.

Hon. D.P.W.

Please explain. The security has already been released.

(Sgd.) C. McI. MESSER,

Treasurer.

23.2.31.

Hon. C. T.

Paragraph 2 of my minute should read "The date due for completion was 7/9/29" but it was not until 20/10/30 that the work was satisfactorily completed. For the reasons given in the minute above referred to only a nominal fine was inflicted.

(Sgd.) H. E. GOLDSMITH,

p. D.P.W.

7.3.31.

Auditor.

For information.

(Sgd.) C. McI. MESSER,

Treasurer.

9.3.31.