Hon. C. S.
A (2) 26
If the Government is satisfied that a two weeks penalty of $200 is sufficient in this case for a delay of 58 weeks on a six months contract for over $16,000 I have nothing more to say.
But I should like definite authority to pass this.
(Sgd.) P. L. COLLISSON,
Auditor.
10.3.31.
Hon. C. S.
I fear I was misled (as I think was the Treasurer) by the words "The date due for completion was 7/9/30" and "The contractor was fined two weeks at $200" at the foot of page 4. The release having been approved and carried through will you approve this retrospectively.
Approved accordingly by command.
(Intd.) N. L. S.
12.3.31.
(Sgd.) E. R. HALLIFAX,
12.3.31
CONTRACT No. 66 of 1929.
Hon. C. S.
Through Hon. Treasurer.
Summarised, the accounting history of this contract is as follows:-
1. Security deposited 22nd November, 1929
2. Work commenced 18th December, 1929
3. Work completed 5th February, 1930
4. Bill submitted March, 1930
5. Amount agreed to May, 1930
6. First and only payment August, 1930
7. No retention money held.
8. Release of security authorised 4th February, 1931 or 60 weeks after the commencement of work on a 7 weeks contract.
Hon. C. S.
A (2) 26
If the Government is satisfied that a two weeks penalty of $200 is sufficient in this case for a delay of 58 weeks on a six months contract for over $16,000 I have nothing more to
But I should like definite authority to pass this.
say.
(Sgd.) P. L. COLLISSON,
Auditor.
10.3.31.
Hon. C. S.
I fear I was misled (as I think was the Treasurer) by the words
"The date due for completion was 7/9/30" and "The contractor was fined two weeks at $200" at the foot of page 4. The release having been approved and carried through will you approve this retrospectively.
Approved accordingly by command.
(Intd.) N. L. S.
12.3.31.
(Sgd.) E. R. HALLIFAX,
12.3.31
CONTRACT No. 66 of 1929.
Hon. C. S.
Through Hon. Treasurer.
Summarised, the accounting history of this contract is as
follows:-
1. Security deposited
2. Work commenced
3. Work completed
4. Bill submitted
5. Amount agreed to
6. First and only payment
7. No retention money held.
22nd November. 1929
18th December, 1929
5th February, 1930
March, 1930
May, 1930
August, 1930
8. Release of security authorised 4th February, 1981
or 60 weeks after the commencement of work on a 7 weeks contract.
No comments yet.