# CONTRACTS FOR PUBLIC WORKS

Contract No. 16 of 1929.

Extracts from C. S. O. File 1184/29.

Contract No. 66 of 1929.

Extracts from C. S. O. File 584/29.

CONTRACT No. 16 of 1929.

Mr. Johnley Ching, the Contractor for Contract No. 16 of 1929--Construction of a 10 feet path to Cape D'Aguilar Wireless Station (1st Section) has applied for the release of his security of $1,250.

2. The work was satisfactorily completed on 20.10.30. The date due for completion was 7.9.30 and the contractor was fined two weeks at $200. The reasons given for delay are as follows:-

1. This work was delayed during the summer of 1929 owing to water shortage and a considerable amount of sickness amongst the workmen.

2. Considerable rainstorm damage during the summer of 1930 delayed the completion of the contract.

In view of the above, the fine inflicted was considered sufficient, and in the circumstances, I recommend his application for approval.

Hon. C. S.

Hon. C. T.

(Sgd.) H. E. GOLDSMITH.

P. D.P.W. 5.2.31.

I agree with above.

(Sgd.) C. McI. MESSER,

Treasurer. 6. 2. 31.

Auditor,

Release approved by command,

(Sgd.) N. L. SMITH.

8. 2.31.

Edit History

2026-05-09 04:17:21 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Hon: C. S. - A (2) 24 Enclosure R. # CONTRACTS FOR PUBLIC WORKS Contract No. 16 of 1929. Extracts from C. S. O. File 1184/29. Contract No. 66 of 1929. Extracts from C. S. O. File 584/29. CONTRACT No. 16 of 1929. Mr. Johnley Ching, the Contractor for Contract No. 16 of 1929--Construction of a 10 feet path to Cape D'Aguilar Wireless Station (1st Section) has applied for the release of his security of $1,250. 2. The work was satisfactorily completed on 20.10.30. The date due for completion was 7.9.30 and the contractor was fined two weeks at $200. The reasons given for delay are as follows:- 1. This work was delayed during the summer of 1929 owing to water shortage and a considerable amount of sickness amongst the workmen. 2. Considerable rainstorm damage during the summer of 1930 delayed the completion of the contract. In view of the above, the fine inflicted was considered sufficient, and in the circumstances, I recommend his application for approval. Hon. C. S. Hon. C. T. (Sgd.) H. E. GOLDSMITH. P. D.P.W. 5.2.31. I agree with above. (Sgd.) C. McI. MESSER, Treasurer. 6. 2. 31. Auditor, Release approved by command, (Sgd.) N. L. SMITH. 8. 2.31.
Baseline (Original)
Hon: C. S. - A (2) 24 Enclosure R. CONTRACTS FOR PUBLIC WORKS. Contract No. 16 of 1929. Extracts from C. S. O. File 1 in 468/29. Contract No. 66 of 1929. Extracts from C. S. O. File 58 in 468/29. CONTRACT No. 16 or 1929. Mr. Johnley Ching, the Contractor for Contract No. 16 of 1929--Construction of a 10 feet path to Cape D'Aguilar Wireless Station (1st Section) has applied for the release of his security of $1,250. 2. The work was satisfactorily completed on 20.10.30. The date due for completion was 7.9.30 and the contractor was fined two weeks at $200. The reasons given for delay are as follows:- 1. This work was delayed during the summer of 1929 owing to water shortage and a considerable amount of sickness amongst the workmen. · 2. Considerable rainstorm damage during the summer of 1930 delayed the completion of the contract. In view of the above, the fine inflicted was considered sufficient, and in the circumstances, I recommend his application for approval. Hon. C. S. Hon. C. T. (Sgd.) H. E. GOLDSMITH. P. D.P.W. 5.2.31. I agree with above. (Sgd.) C. McI. MESSER, Treasurer. 6. 2. 31. Auditor, Release approved by command, (Sgd.) N. L. SMITH. 0 2.31.
2026-05-09 04:17:21 · Baseline
View content

Hon: C. S.

- A (2) 24

Enclosure R.

CONTRACTS FOR PUBLIC WORKS.

Contract No. 16 of 1929.

Extracts from C. S. O. File 1 in 468/29.

Contract No. 66 of 1929.

Extracts from C. S. O. File 58 in 468/29.

CONTRACT No. 16 or 1929.

Mr. Johnley Ching, the Contractor for Contract No. 16 of 1929--Construction of a 10 feet path to Cape D'Aguilar Wireless Station (1st Section) has applied for the release of his security of $1,250.

2. The work was satisfactorily completed on 20.10.30. The date due for completion was 7.9.30 and the contractor was fined two weeks at $200. The reasons given for delay are as follows:-

1. This work was delayed during the summer of 1929 owing to water shortage and a considerable amount of sickness amongst the workmen. ·

2. Considerable rainstorm damage during the summer of 1930 delayed the completion of the contract.

In view of the above, the fine inflicted was considered sufficient, and in the circumstances, I recommend his application for approval.

Hon. C. S.

Hon. C. T.

(Sgd.) H. E. GOLDSMITH.

P. D.P.W. 5.2.31.

I agree with above.

(Sgd.) C. McI. MESSER,

Treasurer. 6. 2. 31.

Auditor,

Release approved by command,

(Sgd.) N. L. SMITH.