4.39
Fitting out of the Flight Information Display System Room was substantially completed in October 1974.
4.40
Work started on the eastward extension of the Main Block of the Terminal Building and the extension of the existing Office Building in February 1975.
4.41
Provision of a pump house and installation of associated water mains were completed by the Waterworks Office in December 1974.
4.42
The installation of Air Navigation Aids on Cheung Chau was completed and handed over to Civil Aviation Department and the installation of Secondary Surveillance Radar on Mount Parker was well advanced at the conclusion of the year.
Education Buildings
4.43
Work on the two new technical institutes, one at Kwun Tong and the other at Kwai Chung, was nearing completion at the end of the year. Piling tenders for the third new institute at Cheung Sha Wan were invited in March 1975.
4.44
The year saw the completion of extensions to the Shau Kei Wan Government Secondary Technical School and the Morrison Hill Technical Institute.
4.45
The Sir Robert Black College of Education was completed and handed over to Education Department in July 1974.
4.46
Further alterations to the Old Northcote Training College were put in hand in February 1975.
Fire Services Buildings
4.47 Satisfactory progress was maintained on the construction of the Ambulance Depot at Mount Davis, due for completion in May 1975.
General Items
4.48
Construction of the Preventive Service Training School at Tai Lam was completed at the end of April 1974.
4.49 To overcome the overcrowding problem in the Macau Ferry Terminal, Stage I of the alterations and additions was completed in April 1974.
4.50 Reprovisioning of the Marine Department Quarters at Tathong Point Light Station was completed during the year as was the reprovisioning of property at Kai Tak Airport for the United Kingdom Department of the Environment.
4.51
In October 1974 the construction of a new building for Radio Hong Kong was also completed.
4.52
Piling work for Stage II of the Multi-Storey Car Park at Yau Ma Tei was completed in December 1974.
36
4.39
Fitting out of the Flight Information Display System Room was substantially completed in October 1974.
4.40
Work started on the eastward extension of the Main Block of the Terminal Building and the extension of the existing Office Building in February 1975.
4.41
Provision of a pump house and installation of associated water mains were completed by the Waterworks Office in December 1974.
4.42
The installation of Air Navigation Aids on Cheung Chau was completed and handed over to Civil Aviation Department and the installation of Secondary Surveillance Radar on Mount Parker was well advanced at the conclusion of the
year.
Education Buildings
4.43
Work on the two new technical institutes, one at Kwun Tong and the other at Kwai Chung, was nearing completion at the end of the year. Piling tenders for the third new institute at Cheung Sha Wan were invited in March 1975.
4.44
The year saw the completion of extensions to the Shau Kei Wan Government Secondary Technical School and the Morrison Hill Technical Institute.
4.45
The Sir Robert Black College of Education was completed and handed over to Education Department in July 1974.
4.46
Further alterations to the Old Northcote Training College were put in hand in February 1975.
Fire Services Buildings
4.47 Satisfactory progress was maintained on the construction of the Ambulance Depot at Mount Davis, due for completion in May 1975.
General Items
4.48
Construction of the Preventive Service Training School at Tai Lam was completed at the end of April 1974.
4.49 To overcome the overcrowding problem in the Macau Ferry Terminal, Stage I of the alterations and additions was completed in April 1974.
4.50 Reprovisioning of the Marine Department Quarters at Tathong Point Light Station was completed during the year as was the reprovisioning of property at Kai Tak Airport for the United Kingdom Department of the Environment.
4.51
In October 1974 the construction of a new building for Radio Hong Kong was also completed.
4.52
Piling work for Stage II of the Multi-Storey Car Park at Yau Ma Tei was completed in December 1974.