# APPENDIX P
# WATERWORKS OFFICE
# WORKS COMPLETED, UNDER CONSTRUCTION AND PROJECTS UNDERTAKEN BY CONSULTANTS
Project Estimated Overall Cost $ (1) Works completed Improved Supplies to Middle Gap, Blacks Link, Shouson Hill and the Ridge, Stage II 200,000 Salt Water Flushing System-Chai Wan Kwun Tong High Level Supply 800,000 ... 5,500,000 Supply to Tsz Wan Shan and Wang Tau Hom Resettlement Estates ... Yau Tong Water Supply Stage II (Extension of Trunk Feed and Construction of Fresh Water Service Reservoir) ... Cheung Chau Water Supply, Stage II ... Peng Chau (Silvermine Bay) Water Supply Stage II ... Water Emergency-Terminals and associated works ... Waterworks Depot Argyle Street, Extensions ... (2) Works under construction Hong Kong Island Chai Wan Distribution System 4,450,000 ... 3,750,000 Chung Hom Kok Fresh Water Supply 1,500,000 Conduit Road Service Reservoir 200,000 Eastern Extension Service Reservoir 1,996,000 Improved Supplies to Mount Cameron and Magazine Gap, Stage II 9,000,000 Pok Fu Lam Supply: (1) Stage I (Queen Mary Hospital) 1,260,000 (2) Stage II 2,400,000 Additional Salt Water Flushing Supplies at Aberdeen ... Salt Water Flushing Systems: (1) Chung Hom Kok 3,500,000 (2) Kennedy Town 760,000 (3) North Point 400,000 Additional Staff Quarters and Chemists' Laboratory at Eastern 700,000 Filters and Pumping Station, Stubbs Road 1,600,000 Reprovisioning of Blake Pier and Rumsey Street Salt Water Pump Houses 450,000 Kowloon and New Kowloon 200,000 Beacon Hill Service Reservoir and Pumping Station ... Trunk Main across Cheung Sha Wan Reclamation 3,620,000 Ham Tin Service Reservoir 600,000 Ho Man Tin Development Supply, Stage II ... Kowloon East Salt Water System (Mains) 4,800,000 6,500,000 1,600,000Page 150
Page 151
APPENDIX P
WATERWORKS OFFICE
WORKS COMPLETED, UNDER CONSTRUCTION AND PROJECTS UNDERTAKEN BY CONSULTANTS
Estimated Overall
Project
Cost
$
(1) Works completed
Improved Supplies to Middle Gap, Blacks Link, Shouson Hill and
the Ridge, Stage II
...
200,000
Salt Water Flushing System-Chai Wan Kwun Tong High Level Supply...
...
800,000
...
5,500,000
Supply to Tsz Wan Shan and Wang Tau Hom Resettlement Estates ... Yau Tong Water Supply Stage II (Extension of Trunk Feed
and Construction of Fresh Water Service Reservoir)
Cheung Chau Water Supply, Stage II ...
Peng Chau (Silvermine Bay) Water Supply Stage II Water Emergency-Terminals and associated works... Waterworks Depot Argyle Street, Extensions...
(2) Works under construction
Hong Kong Island
Chai Wan Distribution System
4,450,000
3,750,000
...
1,500,000
...
1,600,000
4,599,000
...
1,250,000
...
...
1,000,000
Chung Hom Kok Fresh Water Supply
200,000
Conduit Road Service Reservoir
1,996,000
Eastern Extension Service Reservoir
...
9,000,000
Improved Supplies to Mount Cameron and Magazine Gap, Stage II
1,260,000
Pok Fu Lam Supply:
(1) Stage I (Queen Mary Hospital)
2,400,000
(2) Stage II ...
...
Additional Salt Water Flushing Supplies at Aberdeen
Salt Water Flushing Systems:
(1) Chung Hom Kok
(2) Kennedy Town
...
3,500,000
...
760,000
400,000
...
700,000
(3) North Point
...
Additional Staff Quarters and Chemists' Laboratory at Eastern
Filters and Pumping Station, Stubbs Road...
1,600,000
...
450,000
Reprovisioning of Blake Pier and Rumsey Street Salt Water Pump
Houses
...
...
200,000
Kowloon and New Kowloon
Beacon Hill Service Reservoir and Pumping Station... Trunk Main across Cheung Sha Wan Reclamation Ham Tin Service Reservoir
Ho Man Tin Development Supply, Stage II Kowloon East Salt Water System (Mains)
3,620,000
•
600,000
...
...
4,800,000
6,500,000 1,600,000