Project

Kwun Tong New Town Supply: Estimated Overall Cost $ (1) Housing Zones I, II and III and Commercial Centre 510,000 (2) Industrial Zone 5, Section B 155,000 (3) Industrial Zone 5, Section C 110,000 (4) Industrial Zone 5, Section D 200,000 (5) Housing Zones 13 and 14 470,000 Yau Tong Supply, Stage III (Construction of Salt Water Pump House and Reservoir) 1,823,000 Salt Water Flushing Systems: (1) Cheung Sha Wan 3,900,000 (2) Jordan Valley 3,400,000 (3) Kwun Tong 3,350,000 (4) Wong Tai Sin (Kai Tak) 4,700,000 (5) Kwun Tong Jordan Valley Kowloon East Salt Water System (Pumping Station and Additional Mains) 3,250,000 3,650,000 4,600,000 8,000,000 Trunk Supply Mains-Kowloon East 540,000,000 New Territories Castle Peak Water Supply, Raw Water Feed 25,500,000 Plover Cove Scheme, Stage I and II 263,560,000 River Indus Flood Pumping Station and Intake Shek Pik Scheme Sheung Shui-Tai Po Supply, Stage II 11,000,000 Tsing Lung Tau Unfiltered Supply ... Tung Chung Scheme Yuen Long Balance Tank and Pipeline Irrigation Works in the New Territories-Minor Works 850,000 Tsuen Wan/Kwai Chung Development Supply 33,500,000 East River-Sham Chun Scheme 3,200,000 Castle Peak Supply Stage 1A 6,971,000 (3) Projects undertaken by Consultants Shek Pik Water Scheme (except work on Hong Kong Island and catchwaters) Messrs. Binnie & Partners 72,000,000 Tung Chung Scheme 4,524,000 North Western Water Scheme 15,400,000 Plover Cove Water Scheme, Stages I and II (up to and including treatment works) Plover Cove Water Scheme Joint Engineers (Messrs. Binnie & Partners with Messrs. Scott, Wilson, Kirkpatrick & Partners) River Indus Flood Pumping Station and Intake R.K.W. Suez and Associates Water supplies to three resite areas

Page 122

Edit History

2026-05-12 00:21:52 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
APPENDIX P-Contd. Project Kwun Tong New Town Supply: Estimated Overall Cost $ (1) Housing Zones I, II and III and Commercial Centre 510,000 (2) Industrial Zone 5, Section B 155,000 (3) Industrial Zone 5, Section C 110,000 (4) Industrial Zone 5, Section D 200,000 (5) Housing Zones 13 and 14 470,000 Yau Tong Supply, Stage III (Construction of Salt Water Pump House and Reservoir) 1,823,000 Salt Water Flushing Systems: (1) Cheung Sha Wan 3,900,000 (2) Jordan Valley 3,400,000 (3) Kwun Tong 3,350,000 (4) Wong Tai Sin (Kai Tak) 4,700,000 (5) Kwun Tong Jordan Valley Kowloon East Salt Water System (Pumping Station and Additional Mains) 3,250,000 3,650,000 4,600,000 8,000,000 Trunk Supply Mains-Kowloon East 540,000,000 New Territories Castle Peak Water Supply, Raw Water Feed 25,500,000 Plover Cove Scheme, Stage I and II 263,560,000 River Indus Flood Pumping Station and Intake Shek Pik Scheme Sheung Shui-Tai Po Supply, Stage II 11,000,000 Tsing Lung Tau Unfiltered Supply ... Tung Chung Scheme Yuen Long Balance Tank and Pipeline Irrigation Works in the New Territories-Minor Works 850,000 Tsuen Wan/Kwai Chung Development Supply 33,500,000 East River-Sham Chun Scheme 3,200,000 Castle Peak Supply Stage 1A 6,971,000 (3) Projects undertaken by Consultants Shek Pik Water Scheme (except work on Hong Kong Island and catchwaters) Messrs. Binnie & Partners 72,000,000 Tung Chung Scheme 4,524,000 North Western Water Scheme 15,400,000 Plover Cove Water Scheme, Stages I and II (up to and including treatment works) Plover Cove Water Scheme Joint Engineers (Messrs. Binnie & Partners with Messrs. Scott, Wilson, Kirkpatrick & Partners) River Indus Flood Pumping Station and Intake R.K.W. Suez and Associates Water supplies to three resite areas Page 122
Baseline (Original)
APPENDIX P-Contd. Project Kwun Tong New Town Supply: (1) Housing Zones I, II and III and Commercial Centre (2) Industrial Zone 5, Section B ... (3) Industrial Zone 5, Section C + (4) Industrial Zone 5, Section D... (5) Housing Zones 13 and 14 ... ... Yau Tong Supply, Stage III (Construction of Salt Water Pump House and Reservoir)... Salt Water Flushing Systems: (1) Cheung Sha Wan (2) Jordan Valley (3) Kwun Tong ... (4) Wong Tai Sin (Kai Tak) ... ... ... ... ... Estimated Overall Cost $ 510,000 155,000 110,000 200,000 470,000 1,823,000 D 3,900,000 3,400,000 ... 3,350,000 4,700,000 3,250,000 3,650,000 4,600,000 8,000,000 (5) Kwun Tong Jordan Valley Kowloon East Salt Water System (Pumping Station and Additional Mains) ... Trunk Supply Mains-Kowloon East New Territories ... ... Castle Peak Water Supply, Raw Water Feed ... Plover Cove Scheme, Stage I and II River Indus Flood Pumping Station and Intake Shek Pik Scheme Sheung Shui-Tai Po Supply, Stage II Tsing Lung Tau Unfiltered Supply Tung Chung Scheme Yuen Long Balance Tank and Pipeline ... ... ... ... 540,000,000 25,500,000 263,560,000 ... ... A 11,000,000 .. ... ... Irrigation Works in the New Territories-Minor Works Tsuen Wan/Kwai Chung Development Supply East River-Sham Chun Scheme Castle Peak Supply Stage 1A ... (3) Projects undertaken by Consultants Shek Pik Water Scheme (except work on Hong Kong Island and catchwaters) Tung Chung Scheme North Western Water Scheme ... Plover Cove Water Scheme, Stages I and II (up to and including treatment works) River Indus Flood Pumping Station and Intake... ... ... Water supplies to three resite areas ... ... : ... ... ... ... 850,000 33,500,000 3,200,000 6,971,000 72,000,000 4,524,000 15,400,000 Messrs. Binnie & Partners Plover Cove Water Scheme Joint Engineers (Messrs. Binnie & Partners with with Messrs. Scott, Wilson, Kirkpatrick & Partners) R.K.W. Suez and Associates 122
2026-05-12 00:21:52 · Baseline
View content

APPENDIX P-Contd.

Project

Kwun Tong New Town Supply:

(1) Housing Zones I, II and III and Commercial Centre (2) Industrial Zone 5, Section B ...

(3) Industrial Zone 5, Section C

+

(4) Industrial Zone 5, Section D... (5) Housing Zones 13 and 14

...

...

Yau Tong Supply, Stage III (Construction of Salt Water Pump

House and Reservoir)...

Salt Water Flushing Systems:

(1) Cheung Sha Wan

(2) Jordan Valley

(3) Kwun Tong

...

(4) Wong Tai Sin (Kai Tak)

...

...

...

...

...

Estimated Overall

Cost

$

510,000

155,000

110,000

200,000

470,000

1,823,000

D

3,900,000

3,400,000

...

3,350,000

4,700,000

3,250,000

3,650,000

4,600,000

8,000,000

(5) Kwun Tong Jordan Valley Kowloon East Salt Water System (Pumping Station and Additional

Mains)

...

Trunk Supply Mains-Kowloon East

New Territories

...

...

Castle Peak Water Supply, Raw Water Feed ... Plover Cove Scheme, Stage I and II River Indus Flood Pumping Station and Intake Shek Pik Scheme

Sheung Shui-Tai Po Supply, Stage II Tsing Lung Tau Unfiltered Supply

Tung Chung Scheme

Yuen Long Balance Tank and Pipeline

...

...

...

...

540,000,000

25,500,000 263,560,000

...

...

A

11,000,000

..

...

...

Irrigation Works in the New Territories-Minor Works Tsuen Wan/Kwai Chung Development Supply East River-Sham Chun Scheme

Castle Peak Supply Stage 1A

...

(3) Projects undertaken by Consultants

Shek Pik Water Scheme (except work on Hong Kong Island and catchwaters)

Tung Chung Scheme

North Western Water Scheme

...

Plover Cove Water Scheme, Stages I and II (up to and including treatment works) River Indus Flood Pumping Station and

Intake...

...

...

Water supplies to three resite areas

...

...

:

...

...

...

...

850,000

33,500,000

3,200,000 6,971,000 72,000,000

4,524,000 15,400,000

Messrs. Binnie & Partners

Plover Cove Water Scheme Joint Engineers (Messrs. Binnie & Partners with

with Messrs. Scott, Wilson, Kirkpatrick & Partners) R.K.W. Suez and Associates