APPENDIX P-Contd.
Project
Kwun Tong New Town Supply: Estimated Overall Cost $ (1) Housing Zones I, II and III and Commercial Centre 510,000 (2) Industrial Zone 5, Section B 155,000 (3) Industrial Zone 5, Section C 110,000 (4) Industrial Zone 5, Section D 200,000 (5) Housing Zones 13 and 14 470,000 Yau Tong Supply, Stage III (Construction of Salt Water Pump House and Reservoir) 1,823,000 Salt Water Flushing Systems: (1) Cheung Sha Wan 3,900,000 (2) Jordan Valley 3,400,000 (3) Kwun Tong 3,350,000 (4) Wong Tai Sin (Kai Tak) 4,700,000 (5) Kwun Tong Jordan Valley Kowloon East Salt Water System (Pumping Station and Additional Mains) 3,250,000 3,650,000 4,600,000 8,000,000 Trunk Supply Mains-Kowloon East 540,000,000 New Territories Castle Peak Water Supply, Raw Water Feed 25,500,000 Plover Cove Scheme, Stage I and II 263,560,000 River Indus Flood Pumping Station and Intake Shek Pik Scheme Sheung Shui-Tai Po Supply, Stage II 11,000,000 Tsing Lung Tau Unfiltered Supply ... Tung Chung Scheme Yuen Long Balance Tank and Pipeline Irrigation Works in the New Territories-Minor Works 850,000 Tsuen Wan/Kwai Chung Development Supply 33,500,000 East River-Sham Chun Scheme 3,200,000 Castle Peak Supply Stage 1A 6,971,000 (3) Projects undertaken by Consultants Shek Pik Water Scheme (except work on Hong Kong Island and catchwaters) Messrs. Binnie & Partners 72,000,000 Tung Chung Scheme 4,524,000 North Western Water Scheme 15,400,000 Plover Cove Water Scheme, Stages I and II (up to and including treatment works) Plover Cove Water Scheme Joint Engineers (Messrs. Binnie & Partners with Messrs. Scott, Wilson, Kirkpatrick & Partners) River Indus Flood Pumping Station and Intake R.K.W. Suez and Associates Water supplies to three resite areasPage 122
APPENDIX P-Contd.
Project
Kwun Tong New Town Supply:
(1) Housing Zones I, II and III and Commercial Centre (2) Industrial Zone 5, Section B ...
(3) Industrial Zone 5, Section C
+
(4) Industrial Zone 5, Section D... (5) Housing Zones 13 and 14
...
...
Yau Tong Supply, Stage III (Construction of Salt Water Pump
House and Reservoir)...
Salt Water Flushing Systems:
(1) Cheung Sha Wan
(2) Jordan Valley
(3) Kwun Tong
...
•
(4) Wong Tai Sin (Kai Tak)
...
...
...
...
...
Estimated Overall
Cost
$
510,000
155,000
110,000
200,000
•
470,000
1,823,000
D
3,900,000
3,400,000
...
3,350,000
4,700,000
3,250,000
3,650,000
4,600,000
8,000,000
(5) Kwun Tong Jordan Valley Kowloon East Salt Water System (Pumping Station and Additional
Mains)
...
Trunk Supply Mains-Kowloon East
New Territories
...
...
Castle Peak Water Supply, Raw Water Feed ... Plover Cove Scheme, Stage I and II River Indus Flood Pumping Station and Intake Shek Pik Scheme
Sheung Shui-Tai Po Supply, Stage II Tsing Lung Tau Unfiltered Supply
Tung Chung Scheme
Yuen Long Balance Tank and Pipeline
...
...
...
...
540,000,000
25,500,000 263,560,000
...
...
A
11,000,000
..
...
...
Irrigation Works in the New Territories-Minor Works Tsuen Wan/Kwai Chung Development Supply East River-Sham Chun Scheme
Castle Peak Supply Stage 1A
...
(3) Projects undertaken by Consultants
Shek Pik Water Scheme (except work on Hong Kong Island and catchwaters)
Tung Chung Scheme
North Western Water Scheme
...
Plover Cove Water Scheme, Stages I and II (up to and including treatment works) River Indus Flood Pumping Station and
Intake...
...
...
Water supplies to three resite areas
...
...
:
...
...
...
...
850,000
33,500,000
3,200,000 6,971,000 72,000,000
4,524,000 15,400,000
Messrs. Binnie & Partners
Plover Cove Water Scheme Joint Engineers (Messrs. Binnie & Partners with
with Messrs. Scott, Wilson, Kirkpatrick & Partners) R.K.W. Suez and Associates
122