TNAG-2667-FCO40-3864-Hong-Kong-Civil-Service-1993 — Page 52

FCO40 Hong Kong Department Records 聯邦事務部香港部檔案 All

3'

8.

With immediate

responsible for

(a) ensuring

(b)

(c)

effect, he will also

that the works departments (including those whose Directors report to other Branch Secretaries) are effectively deployed so that the projects agreed in the RAS (Category B projects) are made ready to start expeditiously;

to coordinate the resolution of all project-related problems which cannot be quickly resolved at departmental level or below;

to monitor forecast overspending or underspending against the allocations shown against project subheads in the CWRF Estimates, and to take remedial

measures.

be

Public Works Progress Committee (PWPC)

9.

In respect of projects other than the Airport Core Programme (ACP), the Secretary for Works will carry out the above duties with the advice of the PWPC, of which he is the Chairman. The PWPC is already in existence : henceforth, its membership and terms of reference will be revised as set out in the Annex.

10.

Control of the ACP will continue to be exercised through ADSCOM as set out in Financial Circular No. 3/92 dated 23 January 1992.

11.

to

be

The Secretary for Works will continue responsible to the Financial Secretary. Appeals against the decisions of PWPC will be made to the Financial Secretary by Branch Secretaries.

12.

PWPC will in future play a role in the annual Resource Allocation Exercise by advising on the capacity of the works and other related departments to undertake programmes of works put forward by Branch Secretaries to the Star Chamber. Detailed arrangements will be promulgated by the Secretary for the Treasury each year in a circular memorandum.

/13.