Arrangements will also be made in future to obtain PWPC's advice on annual CWRF expenditure Estimates. Detailed arrangements will be announced separately each
year.
Achievement of Targets
14.
Branch Secretaries
and Secretary for Works will work closely to ensure that targets for completing projects in their respective programme areas are met. Existing and future projects should be examined to ensure that adequate lead time is allowed for land acquisition, other statutory procedures and compliance with environmental requirements.
15.
While Branch Secretaries have authority to alter priorities within their programmes, such changes should not, other than in exceptional circumstances, be made once detailed design or land acquisition or other statutory procedures have started. PWPC should be informed of significant changes which are proposed to be made to Branch. Secretaries' programme priorities.
Enquiries
16.
Enquiries about this Circular should be addressed to the Principal Assistant Secretary (Treasury) (Works), telephone no. 810-2232, fax no. 524 2386.
K. Y. YEUNG
Secretary for the Treasury