List of Contracts for New Airport and Related Projects
Brief Scope of Contract
3. TCD Infrastructure - STW/Pumping
Station/Rising Main (Contract No. 5)
Prequalification (P) and Tender (T) Invitation Date
Commencement/ Completion Date
April 1993 (P)
May 1994
November 1993 (T)
to
June 1996
4.
TCD Infrastructure (Contract No. 4)
February 1994 (T)
June 1994
to
June 1996
5.
TCD Infrastructure - Sewage Outfall (Contract No. 6)
August 1993 (P) January 1994 (T)
September 1994
to
June 1996
Managing Department/ Officer-in-Charge
Territory Development
Department (Mr Peter So -
882 7236)
Territory Development Department
(Mr S M N Abbabil - 882 7251)
Territory Development Department (Mr Peter So - 882 7236)
Contractor/ Contract Sum $ M (MOD)
$ 64 M
as at 1st Oct
Origin of Contractor
, 1992
Funding Source/
PWP No.
358CL
PAA
358CL
$ 230 M
358CL
PAA
North Lantau Expressway
6.
Refuse Transfer Station (Contract No. 7)
October 1994
to
December 1996
Environmental Protection
Department (Mr M C Lau -
835 1220)
358CL
PAA
1.
North Lantau Expressway Site Investigation Phase 1 (Contract No. HY/90/23)
15 September 1990 (T)
November 1990
to
May 1991 (Completed)
Highways Department (Mr S C H Wan - 762 3645)
Geotechnics and Concrete Engineering (HK) Ltd. $ 15.88 M (Actual)
HK
468TH
2.
North Lantau Expressway, Tai Ho Section - construction of about 6.6 km of a dual three-lane highway on north Lantau, including site formation for the twin-track airport railway and utility reserve.(incl. watermains) (Contract No. HY/91/07)
9 August 1991 (P)
8 June 1992
16 December 1991 (T)
to
6 October 1996 (Underway)
Highways Department (Mr S C H Wan - 762 3645)
Lantau Expressway Joint Venture
$ 3,059 M
PRC/
New Zealand/
491TH
+
UK/
$ 443 M (excludes $ 443
PRC/
M for AR depot and
associated works)
HK/ Australia