List of Contracts for New Airport and Related Projects

Brief Scope of Contract

Tung Chung Development - Phase I

as at 1st Oc

1992

7. Aircraft Maintenance and Aircargo

Handling Facilities

Prequalification (P) and Tender (T) Invitation Date

Commencement/ Completion Date

3 June 1992 (P) Oct/Nov 1992 (T)

mrid 1993

8.

Airport People Mover System (Contract No. 350)

13 August 1992 (P) Nov/Dec 1992 (T)

June 1993

9.

Aircraft Catering Facilities

14 August 1992 (P) early 1993 (T)

mid 1993

to

early 1995

10. Aviation Fuel Storage/Distribution

(Contract No. 840)

September 1992 (P) December 1992 (T)

To be determined

Managing Department/ Officer-in-Charge

Provisional Airport

Authority

(Mr David Corby - 824 7337)

Provisional Airport Authority

(Mr David Corby - 824 7337)

Provisional Airport Authority

(Mr David Corby - 824 7337)

Provisional Airport Authority (Mr David Corby - 824 7337)

Contractor/ Contract Sum $ M (MOD)

Origin of Contractor

Funding Source/

PWP No.

PAA

PAA

PAA

PAA

1.

North Lantau Development Site Investigation - Preliminary Report Stage (Contract No. IS 11/90)

25 October 1990 (T)

December 1990

to

March 1991 (Completed)

Territory Development Department

Enpack (HK) Ltd. $ 6.65 M

HK

352CL

2. Tung Chung Development, Phase I, Site Formation - 52 ha of reclamation and 15 ha of land formation, together with associated seawalls. (incl. 12 ha of reclamation for NLE Tung Chung Section) (Contract No. NL 1/91)

2 August 1991 (P)

2 December 1991 (T)

2 April 1992

to

March 1994 (Underway)

(Mr T D Armour

882 7250)

Territory Development Department

(Mr S M N Abbabil - 882 7251)

Page No. 2

China Harbour Engineering Company

PRC

383CL

$ 732 M