List of Contracts for New Airport and Related Projects

Brief Scope of Contract

3. TCD Infrastructure - STW/Pumping

Station/Rising Main (Contract No. 5)

Prequalification (P) and Tender (T) Invitation Date

Commencement/ Completion Date

April 1993 (P)

May 1994

November 1993 (T)

to

June 1996

4.

TCD Infrastructure (Contract No. 4)

February 1994 (T)

June 1994

to

June 1996

5.

TCD Infrastructure - Sewage Outfall (Contract No. 6)

August 1993 (P) January 1994 (T)

September 1994

to

June 1996

Managing Department/ Officer-in-Charge

Territory Development

Department (Mr Peter So -

882 7236)

Territory Development Department

(Mr S M N Abbabil - 882 7251)

Territory Development Department (Mr Peter So - 882 7236)

Contractor/ Contract Sum $ M (MOD)

$ 64 M

as at 1st Oct

Origin of Contractor

, 1992

Funding Source/

PWP No.

358CL

PAA

358CL

$ 230 M

358CL

PAA

North Lantau Expressway

6.

Refuse Transfer Station (Contract No. 7)

October 1994

to

December 1996

Environmental Protection

Department (Mr M C Lau -

835 1220)

358CL

PAA

1.

North Lantau Expressway Site Investigation Phase 1 (Contract No. HY/90/23)

15 September 1990 (T)

November 1990

to

May 1991 (Completed)

Highways Department (Mr S C H Wan - 762 3645)

Geotechnics and Concrete Engineering (HK) Ltd. $ 15.88 M (Actual)

HK

468TH

2.

North Lantau Expressway, Tai Ho Section - construction of about 6.6 km of a dual three-lane highway on north Lantau, including site formation for the twin-track airport railway and utility reserve.(incl. watermains) (Contract No. HY/91/07)

9 August 1991 (P)

8 June 1992

16 December 1991 (T)

to

6 October 1996 (Underway)

Highways Department (Mr S C H Wan - 762 3645)

Lantau Expressway Joint Venture

$ 3,059 M

PRC/

New Zealand/

491TH

+

UK/

$ 443 M (excludes $ 443

PRC/

M for AR depot and

associated works)

HK/ Australia

Page No. 3

Page 105Page 106