List of Contracts for New Airport and Related Projects

Brief Scope of Contract

Chek Lap Kok | 1.

Airport

Chek Lap Kok Airport - Land site investigation - airport site (Contract No. PAA 04/90)

2.

3.

Prequalification (P) and Tender (T) Invitation Date

19 November 1990 (T)

Chek Lap Kok Airport - Marine site investigation - airport site (Contract No. PAA 05/90)

19 November 1990 (T)

Airport Advance Works - formation of 29ha of land including 15 ha of reclamation, construction of a 650m long seawall, in the bay area of northern Chek Lap Kok to provide a site to house workers' accommodation and other

facilities as preparatory work. (Contract No. PAA 02/90)

Commencement/ Completion Date

29 December 1990

to

6 May 1991 (Completed)

29 December 1990

to

12 June 1991 (Completed)

16 November 1990 (T)

28 January 1991

4.

Chek Lap Kok Airport - Marine site investigation at Urmston Road & South Tsing Yi (Contract No. PAA 06/90)

22 December 1990 (T)

to

31 July 1992

(Substantial completion) Minor outstanding works completed in September 1992. (Completed)

4 February 1991

to

12 June 1991 (Completed)

Managing Department/ Officer-in-Charge

Provisional Airport Authority (Mr F Uiterwijk - 824 7333)

Provisional Airport Authority (Mr F Uiterwijk - 824 7333)

Provisional Airport Authority (Mr F Uiterwijk - 824 7333)

Provisional Airport Authority (Mr F Uiterwijk - 824 7333)

Contractor/ Contract Sum $ M (MOD)

as at 1st Oer, 1992

Origin of Contractor

Funding Source/ PWP No.

Intrusion-Prepakt (Far East) Ltd. $ 11 M

France

PAA

Bachy Soletanche Group

France

PAA

$ 17.23 M

Kumagai-Ham-Maeda J.V.

$ 336 M

Japan/ PAA Netherlands/

Japan

Gammon Construction

HK

PAA

Ltd.

$ 7.98 M

5. Chek Lap Kok Airport - Marine site

investigation at East Sha Chau (Contract No. PAA 3/91)

16 August 1991 (T)

16 September 1991

to

24 November 1991 (Completed)

Provisional Airport Authority (Mr F Uiterwijk - 824 7333)

Lam Geotechnics Ltd.

$ 6.13 M

HK

PAA

-

6. Airport Site Preparation Contract

excavation of approximately 90 million cu.m of Chek Lap Kok Island and formation of a site of 1250ha for the airport, including construction of seawall & drainage work. (Contract No. PAA 1/91)

15 March 1991 (P)

8 November 1991 (T)

November 1992

to

December 1994

Page No. 1

Provisional Airport Authority (Mr F Uiterwijk - 824 7333)

PAA

$ 9,041 M