NEW AIRPORT AND RELATED PROJECTS
LIST OF CONTRACTS COMPLETED
3 Jun 1991
Contractor/
Brief Scope of Contract
Contract Tender
Date
Contract awarded/| Managing Department/ Contract Completion Dates Officer In-charge
No.
Contract Sum Sm
Funding Source (PWP No.
1. Lantau Fixed Crossing Site Investigation
Phase 5
15 December 1989
March 1990
to November 1990
Highways Department (Mr KS Leung - 721 6540)
HY/89/33 Gammon/Bachy
89TH
Soletanche Joint Venture
$38.2M
2. Route 3 site investigation for road aligment
(CRA 1 route) between Ting Kau and Sham Shui Po.
15 August 1990
to
24 September 1990 Highways Department (Mr
CK Wong - 721 6792)
HY/90/06 Bachy Soletanche
$15.5M
339TH
24 March 1991
3. Route 3 - site investigation for tunnels
15 August 1990
5 September 1990
to
—
Highways Department (Mr CK Wong - 721 6792)
March 1991
HY/90/07 Gammon
Construction $14.5M
339TH
4. North Lantau Expressway Site Investigation
Phase 1
15 September 1990
November 1990
to
Highways Department (Mr CH Wan-721 6029)
HY/90/23 Geotechnics &
Concrete
468TH
May 1991
Engineering (HK) Ltd.
$18.5M
5. North Lantau Development Site Investigation
- Preliminary Report Stage
25 October 1990
December 1990
to March 1991
Territory Development Department (Mr TD Armour 805 6390)
IS 11/90 Enpack (HK) Ltd. $7.73M
352CL
6. Chek Lap Kok Airport - Land site investigation Tendered on
airport site
29 December 1990
Provisional Airport Authority PAA 04/90 Intrusion Prepakt
PAA
19 November 1990
to
(Mr P Leung-802 3490)
(Far East) Lid
6 May 1991
$12.6M