NEW AIRPORT AND RELATED PROJECTS

LIST OF CONTRACTS AWARDED

3 Jun 1991

Civil Engineering

Brief Scope of Contract

1. West Kowloon reclamation - Contract of

Yau Ma Tei Replacement Typhoon Shelter, Phase I

2. Airport Advance Works -- formation of 29ha of

land including 15 ha of reclamation, construction of a 650m long seawall, in the bay area of northern Chek Lap Kok to provide a site 10 house workers' accommodation and other facilities as preparatory works for the airport construction.

3. West Kowloon Reclamation - Construction of Yau Ma Tei Replacement Typhoon Shelter

Contract Tender

Date

Contract awarded/ Completion Dates

Managing Department/ Contract

Officer In-charge

No.

Contractor/ Contract Sum $M

Funding Source (PWP No.

15 June 1990

24 August 1990

Civil Engineering Services

to

Department (Mr CLAu

19 June 1992

-

368 9750)

CV/90/04 Gammon

Construction Ltd.

146CL

$234M

to

Provisional Airport Authority PAA 02/90 Kumagai – Ham – (Mr P Leung-802 3490)

PAA

Macda

29 January 1992

$310.8M

Notice of Prequalification 28 January 1991 gazetted on 24.8.90. Tenders invited from prequalified tenderers on 16 November 1990.

Notice of Prequalification 24 April 1991 gazetted on 10.8.90.

to

Civil Engineering Services Department (Mr CLAu

368 9750)

CV/90/09 Shui on/ Boskalis

j.v.

$1097.29M

146CL 365CL

Phase II and Jordan Road Reclamation Phase I Tenders invited from (Contract No. CV/90/09) - construction of about 4,000m of vertical seawall/revetment,

1 reclamation of about 69ha of land and

reprovisioning of a public cargo working area. The reclaimed land is to provide the landfall for the Western Harbour Crossing, other airport related transport infrastructures and other urban development.

prequalified tenderers on 28 December 1990. Letter of Acceptance of Tender sent to successful bidder on 10 April 1991.

completion date under review subject to availability of site

1. West Kowloon Reclamation Site Investigation

Sile Investigation

2. Chek Lap Kok Airport - Marine site investigation Tendered on

airport site

Tendered on 7 September 1990

19 October 1990

to

Territory Development Department (Mr K

UA 3/90

Lam Geotechnics Lid

354CL

18 October 1991

Austin. 848 2668)

$36.98M

29 December 1990

19 November 1990

to

Provisional Airport Authority PAA 05/90 Bachy Soletanche (Mr P Leung-802 3490)

PAA

28 April 1991

$21.5M

(extended to 12 June 91)

3. Chek Lap Kok Airport - Marine site investigation Works Order issued in

at the Brothers

December 1990

17 December 1990

to

Provisional Airport Authority GCO Term GCO Term (Mr P Leung-802 3490) Contract Contractor

PAA

June 1991

$4.8M

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.