NEW AIRPORT AND RELATED PROJECTS

LIST OF CONTRACTS COMPLETED

3 Jun 1991

Contractor/

Brief Scope of Contract

Contract Tender

Date

Contract awarded/| Managing Department/ Contract Completion Dates Officer In-charge

No.

Contract Sum Sm

Funding Source (PWP No.

1. Lantau Fixed Crossing Site Investigation

Phase 5

15 December 1989

March 1990

to November 1990

Highways Department (Mr KS Leung - 721 6540)

HY/89/33 Gammon/Bachy

89TH

Soletanche Joint Venture

$38.2M

2. Route 3 site investigation for road aligment

(CRA 1 route) between Ting Kau and Sham Shui Po.

15 August 1990

to

24 September 1990 Highways Department (Mr

CK Wong - 721 6792)

HY/90/06 Bachy Soletanche

$15.5M

339TH

24 March 1991

3. Route 3 - site investigation for tunnels

15 August 1990

5 September 1990

to

Highways Department (Mr CK Wong - 721 6792)

March 1991

HY/90/07 Gammon

Construction $14.5M

339TH

4. North Lantau Expressway Site Investigation

Phase 1

15 September 1990

November 1990

to

Highways Department (Mr CH Wan-721 6029)

HY/90/23 Geotechnics &

Concrete

468TH

May 1991

Engineering (HK) Ltd.

$18.5M

5. North Lantau Development Site Investigation

- Preliminary Report Stage

25 October 1990

December 1990

to March 1991

Territory Development Department (Mr TD Armour 805 6390)

IS 11/90 Enpack (HK) Ltd. $7.73M

352CL

6. Chek Lap Kok Airport - Land site investigation Tendered on

airport site

29 December 1990

Provisional Airport Authority PAA 04/90 Intrusion Prepakt

PAA

19 November 1990

to

(Mr P Leung-802 3490)

(Far East) Lid

6 May 1991

$12.6M