ii.
Port Peninsula.
Provision of the reclamation and
the development of the terminals would be timed
to meet the market demand for these facilities.
Provides initial access to the new airport via
the Route Three Lantau Fixed Crossing, which
may be closed for short periods under very severe
weather conditions. This would also apply to
most other exposed road and rail links in Hong
Kong. In addition, the airport itself would have
very restricted operations, or would be closed
under the same conditions.
The same consideration would apply to the
"shorter" bridge proposal.
12. Resource Utilization and Cost Effectiveness
a.
Mr. Gordon Wu's Proposal
i.
The initial capital cost for the transportation infrastructure would be significantly greater than for the core PADS projects completed prior
to 1997.
ii.
The West Kowloon Reclamation, along with the
transport facilities, are required to provide opportunities for environmental improvements for the congested districts of Yau Ma Tei and Mong