II. Project Progress since ATP
1. Implementation of Three Main Contracts
FRA and GEC have placed orders for the most of the main
components of Nuclear Islands and Conventional Islands
respectively. At present, the auxiliary equipment is being
ordered. The manufacturing of main components is on schedule.
Under the Project Services Contract, EdF is providing services
such as design, technical management, training, quality
assurance, etc. including the technical supervision
of the
implementation of the contracts by FRA and GEC, the preparation
of bid specifications for Balance of Plant and civil works.
date, the progress of its contract implementation. is in
accordance with the schedule. Most of the drawings for the
nuclear island civil works have been delivered to site.
To
2.
Site Works
Excavation for the foundations of Unit 1 and Unit 2 Nuclear
Islands has been completed. The blinding concrete of the
gallery and under-raft started on 26th March, 1987 and unit 1
has been completed. The water-proofing concrete of the
gallery started on 23rd April, 1987. Now over 50% has been
completed.
About 84% excavation for the foundation of Conventional
Islands has been completed. Arrangement has been made to perform a first geological inspection of Unit 1 Conventional
Island by the end of May.
61% excavation at the Pumping House and the Water Intake
Channel has been completed. 87% excavation of the Water
Discharge Channel has been
has been completed. It is planned to be
finished within May.
About 56% backfilling and compaction has been completed.