Guangdong Nuclear Power Joint Venture Co., Ltd.
Construction Progress Status
8th May, 1987
Important progress has been achieved in the construction of the
Guangdong Nuclear Power Station under the leadership and with the assistance of the State Council, Ministry of Nuclear Industry, Ministry of Water Resources and Electrical Power and the Guangdong Provincial
Government, the support of various sectors of the society, the
concerted efforts of every main contractor, as well as the joint
efforts of both the Chinese staff and staff from outside of China.
Letters of Intent for the three main contracts (i.e. Nuclear Island
Equipment Supply Contract, Conventional Island Equipment Supply
Contract and Project Services Contract) were signed on 17th April,
1986. Subsequently, these three contracts were officially signed in Beijing on 23rd September, 1986, followed by the notification on the
effectiveness of the contracts (i.e. Authorisation to Proceed) issued
by GNPJVC to the three main contractors on 7th October, 1986. The
construction progress status of the Power Station is hereby given
below.
I.
Main Key Dates
No.
Key Activity
Unit 1
Unit 2
1.
Effectiveness of LoI's
Apr. 86
Apr. 86
2.
Issue of ATP
Oct. 86
Oct. 86
3.
First Structural Raft Concrete
Aug. 87
Apr. 88
4.
Polar Crane put into Operation
Feb. 90
Oct. 90
5.
Containment Pressure Test completed
Aug. 91
Apr. 92
6.
Loading of Nuclear Fuel
Mar. 92
Nov. 92
7.
First Criticality of Reactor
Jun. 92
Feb. 93
8.
Power Supply Network Inter-
Aug. 92
Apr. 93
connected for Generation
9.
Equipment Performance Test
Oct. 92
Jul. 93
completed.