(3) The Director may, by notice to the Road Company,
allow such time additional to the time specified in
subsection (1) as he may determine in the event of -
(a)
storm, flood, natural disaster or other similar
event;
(b) war, insurrection or riot;
(c)
the interruption of the works due to the
non-availability of equipment or materials
essential to the construction works or the
interruption for reasons beyond the control of
the Road Company of the supply of equipment or
materials to the works;
(d) any default or unreasonable delay by the
Government or its agents in doing anything they
are required to do by this Ordinance;
(e)
the undertaking by the Road Company at the
request of the Government of any works which are
not construction works at the commencement of