(3) The Director may, by notice to the Road Company,

allow such time additional to the time specified in

subsection (1) as he may determine in the event of -

(a)

storm, flood, natural disaster or other similar

event;

(b) war, insurrection or riot;

(c)

the interruption of the works due to the

non-availability of equipment or materials

essential to the construction works or the

interruption for reasons beyond the control of

the Road Company of the supply of equipment or

materials to the works;

(d) any default or unreasonable delay by the

Government or its agents in doing anything they

are required to do by this Ordinance;

(e)

the undertaking by the Road Company at the

request of the Government of any works which are

not construction works at the commencement of

Share This Page