this Ordinance, where such undertaking delays the
carrying out of the construction works;
any direction under section 32(2) which is
inconsistent with any approval or exemption
previously given by the Director under Part VI;
any other event which, in the opinion of the
Director, could not reasonably have been foreseen
by the Road Company at the time when it entered
into the project agreement,
and he shall allow such time where this is required by the
terms of any agreement between the Government and the Road
Company for the execution of any works by the Road Company
which are not construction works at the commencement of
this Ordinance, and any period of time so allowed shall be
deemed to extend the period specified in. subsection (1) or,
as the case may be, that period as extended under that
subsection by the period so determined.
Determination
of date of completion.
18.
For the purposes of section 17(1) the date when
the Road Company shall be deemed to have completed the