(a) Chi Ma Wan This is an existing
pa
institution run by the Correctional
Services Department as a Detention Camp
under the Immigration Ordinance and is
Some improvement
immediately available.
and alteration works would be required
but they should not delay the use of the
camp as the works could be done even
after the camp is in use. About 3,500
refugees can be accommodated in its two
sections.
الوريا
(b) Hei Ling Chau A site for the construction
<
of a closed camp for 2,500 is available.
The lead time required for the construction
of this
camp is 9 12 months but it could
J
be made available by phases, the anticipated
completion date of the first phase being
March 1983, with the whole camp being ready
by September 1983. A further 500 could be
accommodated in a nearby institution.
18.
In sum the arrangements set out in paragraphs
15 and 16 above would provide accommodation for the
following number of refugees by the date set out below :