7
-
Progress made and present position
Five meetings have been held so far. Various means to meet the estimated shortfall are being considered.
Next quarter target
To service the Working Party in its deliberations and prepare draft report.
Four meetings of the Review Committee To service the have been held so far. Discussions haveReview Committee focused on the overall objective of in its the Plan and the future development of deliberations. the programme areas.
(a) In August 1980 the Education
Department (ED) took over from the Social Welfare Department (SWD) the World Rehabilitation Fund Day Centre for the provision of vocational training. Two additional floors will be completed by December 1981 to provide an additional 84 training places for the disabled and the establishment of a Vocational Assessment Centre.
(b) DSW is considering in conjunction
with the Director of Housing taking over one of the 3 school premises in public housing estates offered by D of E to accommodate services to be transferred out of the World Rehabilitation Fund Day Centre.
(c) A revised draft Code of Aid has
been received from D of E and is under consideration in the Social Services Branch.
To monitor progress.
To monitor progress
機密
CONFIDENTIAL
To seek RDCC advice on the draft Code.
No comments yet.
Private notes are available after approval.