LANDS AND WORKS BRANCH PROGRESS REPORT

1st August to 31st October 1981

Part I

CONFIDENTIAL # m

LANDS DIVISION

Purpose

Subject

(a) Junk Bay

(LW(SPU)70/61/

02)

(e) Harbour Recl-

amations and

Urban Growth

(LW(SPU)70/61/

14)

Progress Made & Present Position

(d) Junk Bay

Consultants continued with the Junk Bay development study and submitted

Interim Report. The Land Development Policy Committee endorsea the consultants' interim recommends -- tions and agreed that a programme should be drawn up for the removal of existing industries compromising development and that the Mass Transit Railway Corporation should be consulted over the fessibility of the MTR providing the principal external access to the new town.

(e) Harbour Reclamations and Urtan Growth

Negotiations with the selected. consultants continued.

Next Quarter Targets

(d) Junk Bay

Proceed with action. agreed by LDIC and monitor progress of remainder of Junk Bay study (completion late 1982).

(e) Harbour Reclamations

and Urban Growth

Appoint consultants and commence study (completion mid 1983).