LANDS AND WORKS BRANCH PROGRESS REPORT
1st August to 31st October 1981
Part I
CONFIDENTIAL # m
LANDS DIVISION
Purpose
Subject
(a) Junk Bay
(LW(SPU)70/61/
02)
(e) Harbour Recl-
amations and
Urban Growth
(LW(SPU)70/61/
14)
Progress Made & Present Position
(d) Junk Bay
Consultants continued with the Junk Bay development study and submitted
Interim Report. The Land Development Policy Committee endorsea the consultants' interim recommends -- tions and agreed that a programme should be drawn up for the removal of existing industries compromising development and that the Mass Transit Railway Corporation should be consulted over the fessibility of the MTR providing the principal external access to the new town.
(e) Harbour Reclamations and Urtan Growth
Negotiations with the selected. consultants continued.
Next Quarter Targets
(d) Junk Bay
Proceed with action. agreed by LDIC and monitor progress of remainder of Junk Bay study (completion late 1982).
(e) Harbour Reclamations
and Urban Growth
Appoint consultants and commence study (completion mid 1983).