Prices

the design and supply of overhead transmission lines and crossing towers from the new power station to

anchor towers on the mainland.

the supply of 2 x 50 Mw gas turbine units.

Station design and supply, on a c.i.f.. basis, of the equipment

for the initial 2 x 350 Mw units:

Supply of additional option 2 x 350 Mw units, on a c.i.f. basis, if the option is taken up by 1 November 1979:

£

Design and supply, c.i.f. of overhead transmission lines

and crossing towers from the new power station to anchor

towers on the mainland:

£

Supply of 2 x 50 Mw gas turbine units, on c.i.f. basis:

£

All c.i.f. prices are based upon prevailing freight rates and might have to be adjusted in the light of market conditions.

CEGB Services

The technical consultancy services of the British Electricity International CEGB, will be provided to assist CLP/PEPCO in the establishment of the power station and high voltage transmission link. In particular BEI will:

advise on site development work;

assist CLP/PEPCO in monitoring the contractors' activities in the UK;

review the design of all plant and equipment and

the system designs for the station;