TNAG-0424-FCO40-470-Construction-of-an-underground-railway-system-in-Hong-Kong-1973 — Page 245

FCO40 Hong Kong Department Records 聯邦事務部香港部檔案 All

0003160 G.F. 316

SECRET

Other Finance

14

The Consortium's financial advisers have offered to act as financial advisers to the MTR Corporation, and to assist in arranging bond issues, medium-term bank loans and other market finance, if required or desired by the client.

Construction/Equipment Aspects

15

The Consortium propose to commence construction on 1st April 1974, and have indicated a maximum construction period of five years from the date of commencement.

16

They intend to use the most advanced construction methods available, with a view to minimising labour requirements.

17

They will assist in organising and/or providing training facilities for the MTR Corporation's operations staff. They would also provide for a period of test operations in respect of the rolling stock and E & M equipment supplied.

Additional Work Required of Consulting Engineers

18

Before they could take over the detailed design of the system, the Consortium would require from the Consulting Engineers:

(a) details of soil conditions throughout the network;

(b)

(c)

details of the nature, location and extent of utility services;

details of the nature and type of foundations of buildings fronting or close to the MTR works;

(d) 1/500 topographical maps showing the route alignment;

(e) 1/200 topographical maps in the neighbourhood of stations

giving overall dimensions and details of ventilation shafts and station entrances; and

(f)

performance specifications as regards E & M supplies.

Proposed Sequence of Events

19

The Consortium's proposal to commence construction on 1st

April 1974 is predicated on the assumptions that:

(a) they would receive a Letter of Intent by 1st October 1973 signifying the client's intention to negotiate a contract with them;

(b)

(c)

information on soil conditions would be made available by the Consulting Engineers progressively as it is ready;

other basic data and design parameters for civil works and performance specifications for E & M supplies would also be made available progressively, and would be completed by January 1974; and

(d) negotiations on the contract would be completed before the

end of March 1974.

:

SECRET

/.... 20