There are a library. assembly hall, and covered playground. Additional amenities include laboratories for chemistry, physics and biology, a geography room, a projection room. and refectory for
for students and teachers.
There are also 11 quarters for the Fathers.
A seven-passenger lift in the school was manufactured by G. Falconi & C.S.A.. of Novara, Italy, and is the first of its make to be installed in Hong Kong.
Falconi manufacture under licence from Westinghouse, and to their
designs. Orders are being executed for Falconi lifts in two other new buildings in Hong Kong.
The Hong Kong & China Gas Co., Ltd., carried out the laboratory gas installation.
General contractor: Yao Kee
Construction Co.
Windows: China Steel Works. Ltd. Waterproofing:
(H.K.) Ltd.
Sino British
Lift: Falconi, supplied by Yee
CLASS ROOM CLASS
ASS
T TALENTY
TEACHERS
ROOM
COVERED
PLAYGROUND
OPEN
PLAYGROUND
ROOM
COVERED PLAYGROUND
PASSAGE
CLASS ROOM CLASS
ROOM
EXISTING BUILDING
Above, first floor plan (left) and ground floor.
from rear field.
DILA
I
ALON
TEACHERS
Below, new wing seen
On Hong Co. Ltd.
SINGAPORE GOVERNMENT CONTRACTS AWARDED
PARTICULARS
CONTRACTORS
June, 1960
Construction of proposed landing facilities at Tuas, Jurong
Road
Construction of one "mixed" three storey secondary school,
assembly hall, combined domestic science and science block, tiffin shed and servants' quarters at Queenstown Neighbourhood II
Earthworks at site of proposed "mixed" secondary school,
Upper Aljunied Rd.
Internal re-decoration and general repairs, etc., to Outram Rd. School, servants' quarters. tiffin shed and scouts' shed
+
Distempering, painting and repairs to upper office, herbarium,
lower office and lavatories at Botanical Gardens General repairs and re-decoration, etc. to Police guard room,
canteen, garage and kitchen Government House Construction of a reformative training centre (phase 3) at
Changi Rd., Bedok
Construction of two buildings for Commercial Broadcasting
Service, Radio Singapore, Caldecott Hill
Execution of earthworks, turfing, etc. at site of proposed
primary school Silat Rd.
Construction of bus terminus, taxi stand and other ancillary
works, Serangoon Garden Way
LLL
Earthworks, turfing etc, at site of proposed primary and secondary schools, Ngee Ann Kongsi, Balestier Rd. Construction of standard primary schoo!, tiffin shed and
servants' quarters at Outram Rd.
THE HONG KONG & FAR EAST BUILDER VOLUME 15. NUMBER 2
Song Hup Seng
Woh Hup Ltd.
Song Hup Seng
Chua Tua Chai
Seah Lye Huat
Seah Lye Huat
Ho Bock Kee
..
Hup Lee Seng Const. Co.
Hoe Ann Contractor
:
⠀
:
Shanghai Structural Contractor
Song Hup Seng.
Ho Hock Swee
1967
AMOUNT SM.
13,825.00
506,000.00
9.750.00
13.769.76
4,729.05
4,736.54
752,000.00
73.204.17
8,001.55
13,171.00
78,308.90
212,662.86