193. Pier at Aplichau for Urn Cemetery :-To facilitate the landing of urns and headstones to the far side of Aplichau Island by the Sanitary Department, a contract was let to Messrs. Chung Lee & Co. for the erection of a small pier and causeway approach. This was completed satisfactorily in July, 1935, and the expenditure, which was small, was met by the Sanitary Department.

194. Dredging for Harbour Improvements:-During the year, dredging was undertaken in the Central Fairway and West of Kowloon Peninsula on behalf of the Admiralty and the Hong Kong and Kowloon Wharf & Godown Company. The cost was proportionately shared.

195. Sewer at North Point:-The construction of the septic tank on the foreshore together with a storage tank, pump house, and the installation of a 3" diameter centrifugal sewage pump were completed in August and the system has been working satisfactorily since that date.

Expenditure
$ 7,858.10

196. Resumption of St. Peter's Church, West Point:-It was resolved to pay out the compensation money in instalments as the new church progressed.

197. Resumption of Aplichau Squatters' Claims:-In connection with the development of Aplichau village the resumption of the outstanding claims was completed.

Expenditure
$ 6,509.10

198. Telephone Cable to Shaukiwan:-Telephone underground cable was laid from Wongneichong to Shaukiwan Road (now called King's Road).

Expenditure
$ 524.34

199. Beacon Transmitter:-Type WB2b Beacon Transmitter and duplicate Generators were received and installed at Cape D'Aguilar Transmitting Station.

Expenditure
$ 8,632.73

200. H.M. The King's Jubilee :-Certain electrical work, temporary lights, telephone, bells, etc. were installed in connection with the Jubilee Celebration.

Expenditure
$ 10,380.27

201. Demolition of the "World" Pencil Factory, Kai Tak Airport-The work of demolition which was commenced in May and completed in July was carried out by Messrs. Koon Tai & Co. A credit of $1,250.00 was received from them for the old materials.

Expenditure
$ 442.97

Edit History

2026-05-09 23:51:02 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
193. Pier at Aplichau for Urn Cemetery :-To facilitate the landing of urns and headstones to the far side of Aplichau Island by the Sanitary Department, a contract was let to Messrs. Chung Lee & Co. for the erection of a small pier and causeway approach. This was completed satisfactorily in July, 1935, and the expenditure, which was small, was met by the Sanitary Department. 194. Dredging for Harbour Improvements:-During the year, dredging was undertaken in the Central Fairway and West of Kowloon Peninsula on behalf of the Admiralty and the Hong Kong and Kowloon Wharf & Godown Company. The cost was proportionately shared. 195. Sewer at North Point:-The construction of the septic tank on the foreshore together with a storage tank, pump house, and the installation of a 3" diameter centrifugal sewage pump were completed in August and the system has been working satisfactorily since that date. Expenditure $ 7,858.10 196. Resumption of St. Peter's Church, West Point:-It was resolved to pay out the compensation money in instalments as the new church progressed. 197. Resumption of Aplichau Squatters' Claims:-In connection with the development of Aplichau village the resumption of the outstanding claims was completed. Expenditure $ 6,509.10 198. Telephone Cable to Shaukiwan:-Telephone underground cable was laid from Wongneichong to Shaukiwan Road (now called King's Road). Expenditure $ 524.34 199. Beacon Transmitter:-Type WB2b Beacon Transmitter and duplicate Generators were received and installed at Cape D'Aguilar Transmitting Station. Expenditure $ 8,632.73 200. H.M. The King's Jubilee :-Certain electrical work, temporary lights, telephone, bells, etc. were installed in connection with the Jubilee Celebration. Expenditure $ 10,380.27 201. Demolition of the "World" Pencil Factory, Kai Tak Airport-The work of demolition which was commenced in May and completed in July was carried out by Messrs. Koon Tai & Co. A credit of $1,250.00 was received from them for the old materials. Expenditure $ 442.97
Baseline (Original)
-0:55 193. Pier at Aplichau for Urn Cemetery :-To facilitate the landing of urns and headstones to the far side of Aplichau Island by the Sanitary Department, a contract was let to Messrs. Chung Lee & Co. for the erection of a small pier and causeway approach. This was completed satisfactorily in July, 1935, and the expendi ture, which was small was met by the Sanitary Department. 194. Dredging for Harbour Improvements:-During the year, dredging was undertaken in the Central Fairway and West of Kowloon Peninsula on behalf of the Admiralty and the Hong Kong and Kowloon Wharf & Godown Company. The cost was. proportionately shared. 195. Sewer at North Point:-The construction of the septic tank on the foreshore together with a storage tank, pump house, and the installation of a 3" diameter centrifugal sewage pump were completed in August and the system has been working satisfactorily since that date. Expenditure $ 7,858.10 196. Resumption of St. Peter's Church, West Point: -It was resolved to pay out the compensation money in instalments as the new church progressed. 197. Expenditure .$ 6,509:10 Resumption of Aplichau Squatters' Claims:-In con- nection with the development of Aplichau village the resumption of the outstanding claims was completed. Expenditure 198. $ 524.34 Telephone Cable to Shaukiwan:-Telephone under- ground cable was laid from Wongneichong to Shaukiwan Road (now called King's Road). Expenditure $ 8,632.73 199. Beacon Transmitter:-Type WB2b Beacon Trans- smitter and duplicate Generators were received and installed at Cape D'Aguilar Transmitting Station. Expenditure $ 10,380.27 200. H.M. The King's Jubilee :-Certain electrical work, temporary lights, telephone, bells, etc. were installed in connec- tion with the Jubilee Celebration. Expenditure $ 442.97 201. Demolition of the "World" Pencil Factory, Kai Tak Airport-The work of demolition which was commenced in May and completed in July was carried out by Messrs. Koon Tai & Co. A credit of $1,250.00 was received from them for the old materials.
2026-05-09 23:51:02 · Baseline
View content

-0:55

193. Pier at Aplichau for Urn Cemetery :-To facilitate the landing of urns and headstones to the far side of Aplichau Island by the Sanitary Department, a contract was let to Messrs. Chung Lee & Co. for the erection of a small pier and causeway approach. This was completed satisfactorily in July, 1935, and the expendi ture, which was small was met by the Sanitary Department.

194. Dredging for Harbour Improvements:-During the year, dredging was undertaken in the Central Fairway and West of Kowloon Peninsula on behalf of the Admiralty and the Hong Kong and Kowloon Wharf & Godown Company. The cost was. proportionately shared.

195. Sewer at North Point:-The construction of the septic tank on the foreshore together with a storage tank, pump house, and the installation of a 3" diameter centrifugal sewage pump were completed in August and the system has been working satisfactorily since that date.

Expenditure

$ 7,858.10

196. Resumption of St. Peter's Church, West Point: -It was resolved to pay out the compensation money in instalments as the new church progressed.

197.

Expenditure

.$ 6,509:10

Resumption of Aplichau Squatters' Claims:-In con- nection with the development of Aplichau village the resumption of the outstanding claims was completed.

Expenditure

198.

$ 524.34

Telephone Cable to Shaukiwan:-Telephone under- ground cable was laid from Wongneichong to Shaukiwan Road (now called King's Road).

Expenditure

$ 8,632.73

199. Beacon Transmitter:-Type WB2b Beacon Trans- smitter and duplicate Generators were received and installed at Cape D'Aguilar Transmitting Station.

Expenditure

$ 10,380.27

200. H.M. The King's Jubilee :-Certain electrical work, temporary lights, telephone, bells, etc. were installed in connec- tion with the Jubilee Celebration.

Expenditure

$ 442.97

201. Demolition of the "World" Pencil Factory, Kai Tak Airport-The work of demolition which was commenced in May and completed in July was carried out by Messrs. Koon Tai & Co. A credit of $1,250.00 was received from them for the old materials.