COMMUNICATIONS.

138. Chatham Road Extension.--This work was referred to in paragraph 229 of last year's Report. The Contract was satisfactorily completed on 1st November, 1932.

1932 Expenditure $58,088.90

Expenditure to 31st Dec., 1932... $157,762.91

139. Improving existing main roads for motor traffic. Portions of Nathan Road, Prince Edward Road and Lai Chi Kok Road were reconditioned and strengthened with 7" re-inforced cement concrete surfacing.

Expenditure $75,522.44

MISCELLANEOUS.

140. Exhumation of Chinese Cemeteries.--No expenditure was incurred.

141. Chinese Cemeteries-Laying out new areas.--Work carried out under this head is also alluded to in paragraph 32 of this Report.

Expenditure $4,997.38

142. Refuse Dump at Sung Wong Toi.--The contract for this work was awarded to Messrs. Sang Lee & Co.

The progress was satisfactory. The contract was handed over to Port Development Office on 31st December, 1932.

Expenditure $5,898.57

143. Rewiring of Government Buildings Nos. 1 to 6 Cox's Path; 1 to 8 Cox's Road; Reclamation Street Market and Royal Observatory were completely rewired for fans and lights. Work on rewiring of Yaumati Police Station was commenced but not completed.

Expenditure $8,492.90

144. Rewiring of Yaumati Government School.--Rewired for electric lights and fans.

Expenditure $1,174.49

145. Resumption of Ma Tau Wei Village.--Expenditure incurred in connection with the removal of the village owing to Town Planning.

Expenditure $10,454.91

Edit History

2026-05-09 10:51:15 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Q 37 COMMUNICATIONS. 138. Chatham Road Extension.--This work was referred to in paragraph 229 of last year's Report. The Contract was satisfactorily completed on 1st November, 1932. 1932 Expenditure $58,088.90 Expenditure to 31st Dec., 1932... $157,762.91 139. Improving existing main roads for motor traffic. Portions of Nathan Road, Prince Edward Road and Lai Chi Kok Road were reconditioned and strengthened with 7" re-inforced cement concrete surfacing. Expenditure $75,522.44 MISCELLANEOUS. 140. Exhumation of Chinese Cemeteries.--No expenditure was incurred. 141. Chinese Cemeteries-Laying out new areas.--Work carried out under this head is also alluded to in paragraph 32 of this Report. Expenditure $4,997.38 142. Refuse Dump at Sung Wong Toi.--The contract for this work was awarded to Messrs. Sang Lee & Co. The progress was satisfactory. The contract was handed over to Port Development Office on 31st December, 1932. Expenditure $5,898.57 143. Rewiring of Government Buildings Nos. 1 to 6 Cox's Path; 1 to 8 Cox's Road; Reclamation Street Market and Royal Observatory were completely rewired for fans and lights. Work on rewiring of Yaumati Police Station was commenced but not completed. Expenditure $8,492.90 144. Rewiring of Yaumati Government School.--Rewired for electric lights and fans. Expenditure $1,174.49 145. Resumption of Ma Tau Wei Village.--Expenditure incurred in connection with the removal of the village owing to Town Planning. Expenditure $10,454.91
Baseline (Original)
- Q 37 COMMUNICATIONS. 138. Chatham Road Extension,--This work was referred to in paragraph 229 of last year's Beport. The Contract was satis- factorily completed on 1st November, 1932. 1932 Expenditure $ 58,088.90 Expenditure to 31st Dec., 1932... $157,762.91 139. Improving existing main roads for motor traffic. Portions of Nathan Road, Prince Edward Road and Lai Chi Kok Road were reconditioned and strengthened with 7" re-inforced cement concrete surfacing. Expenditure MISCELLANEOUS. $75,522.44 140. Exhumation of Chinese Cemeteries.-No expenditure was incurred. 141. Chinese Cemeteries-Laying out new areas. -Work carried out under this head is also alluded to in paragraph 32 of this Report. Expenditure $4,997.38 142. Refuse Dump at Sung Wong Toi.-The contract for this work was awarded to Messrs. Sang Lee & Co. The progress was satisfactory. The contract was handed over to Port Development Office on 31st December, 1932. Expenditure $5,898.57 143. Rewiring of Government Buildings Nos. 1 to 6 Cox's Path; 1 to 8 Cox's Road; Reclamation Street Market and Royal Observatory were completely rewired for fans and lights. Work on rewiring of Yaumati Police Station was commenced but not completed. Expenditure $8,492.90 144. Rewiring of Yaumati Government School.---Rewired for electric lights and fans. Expenditure $1,174.49 145. Resumption of Ma Tau Wei Village.-Expenditure incurred in connection with the removal of the village owing to Town Planning. Expenditure $10,454.91.
2026-05-09 10:51:15 · Baseline
View content

- Q 37

COMMUNICATIONS.

138. Chatham Road Extension,--This work was referred to in paragraph 229 of last year's Beport. The Contract was satis- factorily completed on 1st November, 1932.

1932 Expenditure

$ 58,088.90

Expenditure to 31st Dec., 1932... $157,762.91

139. Improving existing main roads for motor traffic. Portions of Nathan Road, Prince Edward Road and Lai Chi Kok Road were reconditioned and strengthened with 7" re-inforced cement concrete surfacing.

Expenditure

MISCELLANEOUS.

$75,522.44

140. Exhumation of Chinese Cemeteries.-No expenditure was incurred.

141. Chinese Cemeteries-Laying out new areas. -Work carried out under this head is also alluded to in paragraph 32 of this Report.

Expenditure

$4,997.38

142. Refuse Dump at Sung Wong Toi.-The contract for this work was awarded to Messrs. Sang Lee & Co.

The progress was satisfactory. The contract was handed over to Port Development Office on 31st December, 1932.

Expenditure

$5,898.57

143. Rewiring of Government Buildings Nos. 1 to 6 Cox's Path; 1 to 8 Cox's Road; Reclamation Street Market and Royal Observatory were completely rewired for fans and lights. Work on rewiring of Yaumati Police Station was commenced but not completed.

Expenditure

$8,492.90

144. Rewiring of Yaumati Government School.---Rewired for electric lights and fans.

Expenditure

$1,174.49

145. Resumption of Ma Tau Wei Village.-Expenditure incurred in connection with the removal of the village owing to Town Planning.

Expenditure

$10,454.91.