Loan Works.

Q 46

278. Item 7, Pipe Line.-This work was referred to in paragraph 250 Item 7 of last year's Report. By the end of July the Pipe Line was completed and brought into operation, delivering water to the Elliot Slow Sand Filters by means of the subsidiary 12″ dia. connection. On completion of the new Fast Gravity Beds water was delivered directly to them. The pipe line which consists of 18" and 21" effective dia. steel tubes 1" thick having 1″ thick bitumastic internal lining and bitumen impregnated hessian single wrapping outside is divided into the following sections:

Aberdeen Upper Dam to Lower Pumping Station 18" internal dia. 4,980 lineal feet Lower Pumping Station to Telegraph Bay Syphon 18” internal dia. 11,965 Telegraph Bay Syphon (steel 9/32″ thick 18″ internal dia.) Telegraph Bay Syphon to Sandy Bay Gap 18" internal dia. 1,200 Sandy Bay Gap open cuts & Tunnel to Gauge Basin.. 1J Sandy Bay Gap to Elliot Rapid Gravity Beds 21" internal dia. 3,363 ܙ 546

279. The pipe line at Telegraph Bay Syphon is designed to take an additional pressure from Pokfulam Reservoir and consists of 18" effective dia. steel tubes 9/32" thick having " thick bitumastic internal lining and hessian outside wrapping as above. The connection from Pokfulam Reservoir has not yet been laid.

280. The Upper Pumping Station is connected by means of an 18" internal dia. steel branch main and the slow sand beds at Elliot are connected by a subsidiary 12″ internal dia. steel main.

Invert Level of Inlet Pipe at Sandy Bay Gap... O.D. 307.50 Level of 4′-0″ gauge at Sandy Bay Gap. 307.00 Invert of Outlet Pipe at Sandy Bay Gap... 303.63 Invert of Inlet Pipe to Elliot Rapid Gravity Filters 297.00 Invert Level of Tunnel at Sandy Bay Gap........... 306.00

281. Item 8, Pumping Station-Aberdeen Upper Pumping Station. This work was referred to in paragraph 250 Item 8 of last year's Report. A contract for the building of the Pumping Station was let to Messrs. Kin Lee & Co. on 4th May, 1931 for $5,372.95 By the end of August the building contract was finished and by the end of September the installation of the pump and electric motor completed. After successful tests in October the pump was put into operation in pumping out the

Edit History

2026-05-09 08:25:51 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Loan Works. Q 46 278. Item 7, Pipe Line.-This work was referred to in paragraph 250 Item 7 of last year's Report. By the end of July the Pipe Line was completed and brought into operation, delivering water to the Elliot Slow Sand Filters by means of the subsidiary 12″ dia. connection. On completion of the new Fast Gravity Beds water was delivered directly to them. The pipe line which consists of 18" and 21" effective dia. steel tubes 1" thick having 1″ thick bitumastic internal lining and bitumen impregnated hessian single wrapping outside is divided into the following sections: Aberdeen Upper Dam to Lower Pumping Station 18" internal dia. 4,980 lineal feet Lower Pumping Station to Telegraph Bay Syphon 18” internal dia. 11,965 Telegraph Bay Syphon (steel 9/32″ thick 18″ internal dia.) Telegraph Bay Syphon to Sandy Bay Gap 18" internal dia. 1,200 Sandy Bay Gap open cuts & Tunnel to Gauge Basin.. 1J Sandy Bay Gap to Elliot Rapid Gravity Beds 21" internal dia. 3,363 ܙ 546 279. The pipe line at Telegraph Bay Syphon is designed to take an additional pressure from Pokfulam Reservoir and consists of 18" effective dia. steel tubes 9/32" thick having " thick bitumastic internal lining and hessian outside wrapping as above. The connection from Pokfulam Reservoir has not yet been laid. 280. The Upper Pumping Station is connected by means of an 18" internal dia. steel branch main and the slow sand beds at Elliot are connected by a subsidiary 12″ internal dia. steel main. Invert Level of Inlet Pipe at Sandy Bay Gap... O.D. 307.50 Level of 4′-0″ gauge at Sandy Bay Gap. 307.00 Invert of Outlet Pipe at Sandy Bay Gap... 303.63 Invert of Inlet Pipe to Elliot Rapid Gravity Filters 297.00 Invert Level of Tunnel at Sandy Bay Gap........... 306.00 281. Item 8, Pumping Station-Aberdeen Upper Pumping Station. This work was referred to in paragraph 250 Item 8 of last year's Report. A contract for the building of the Pumping Station was let to Messrs. Kin Lee & Co. on 4th May, 1931 for $5,372.95 By the end of August the building contract was finished and by the end of September the installation of the pump and electric motor completed. After successful tests in October the pump was put into operation in pumping out the
Baseline (Original)
Loan Works. Q 46 278. Item 7, Pipe Line.-This work was referred to in para- graph 250 Item 7 of last year's Report. By the end of July the Pipe Line was completed and brought into operation, deliver- ing water to the Elliot Slow Sand Filters by means of the sub- sidiary 12′′ dia. connection. On completion of the new Fast Gravity Beds water was delivered directly to them. The pipe line which consists of 18" and 21" effective dia, steel tubes 1" thick having 1′′ thick bitumastic internal lining and bitumen im- pregnated hessian single wrapping outside is divided into the following sections: Aberdeen Upper Dam to Lower Pumping Station 18" internal dia. 4,980 lineal feet Lower Pumping Station to Telegraph ... Bay Syphon 18” internal dia. 11,965 Telegraph Bay Syphon (steel 9/32′′ thick 18′′ internal dia.) Telegraph Bay Syphon to Sandy Bay Gap 18" internal dia. Sandy Bay Gap open cuts & Tunnel to Gauge Basin.. Sandy Bay Gap to Elliot Rapid Grav- ity Beds 21" internal dia. 1,200 1J 4,343 546 3,363 ܙ 279. The pipe line at Telegraph Bay Syphon is designed to take an additional pressure from Pokfulam Reservoir and consists of 18" effective dia. steel tubes 9/32" thick having " thick bitumastic internal dining and hessian outside wrapping as above. The connection from Pokfulam Reservoir has not yet been laid. 280. The Upper Pumping Station is connected by means of an 18" internal dia, steel branch main and the slow sand beds at Elliot are connected by a subsidiary 12′′ internal dia. steel main. Invert Level of Inlet Pipe at Sandy Bay Gap... Invert Level of Tunnel at Sandy Bay Gap........... O.D. 307.50 Level of 4′-0′′ gauge at Sandy Bay Gap. Invert of Outlet Pipe at Sandy Bay Gap... Invert of Inlet Pipe to Elliot Rapid Gravity Filters 306.00 307.00 303.63 297.00 281. Item 8, Pumping Station-Aberdeen Upper Pumping Station. This work was referred to in paragraph 250 Item 8 of last year's Report. A contract for the building of the Pumping Station was let to Messrs. Kin Lee & Co. on 4th May, 1931 for $5,372.95 By the end of August the building contract was finished and by the end of September the installation of the pump and electric motor completed. After successful tests in October the pump was put into operation in pumping out the
2026-05-09 08:25:51 · Baseline
View content

Loan Works.

Q 46

278. Item 7, Pipe Line.-This work was referred to in para- graph 250 Item 7 of last year's Report. By the end of July the Pipe Line was completed and brought into operation, deliver- ing water to the Elliot Slow Sand Filters by means of the sub- sidiary 12′′ dia. connection. On completion of the new Fast Gravity Beds water was delivered directly to them. The pipe line which consists of 18" and 21" effective dia, steel tubes 1" thick having 1′′ thick bitumastic internal lining and bitumen im- pregnated hessian single wrapping outside is divided into the following sections:

Aberdeen Upper Dam to Lower

Pumping Station 18" internal dia. 4,980 lineal feet

Lower Pumping Station to Telegraph

...

Bay Syphon 18” internal dia. 11,965 Telegraph Bay Syphon (steel 9/32′′

thick 18′′ internal dia.)

Telegraph Bay Syphon to Sandy Bay

Gap 18" internal dia.

Sandy Bay Gap open cuts & Tunnel

to Gauge Basin..

Sandy Bay Gap to Elliot Rapid Grav-

ity Beds 21" internal dia.

1,200

1J

4,343

546

3,363

ܙ

279. The pipe line at Telegraph Bay Syphon is designed to take an additional pressure from Pokfulam Reservoir and consists of 18" effective dia. steel tubes 9/32" thick having " thick bitumastic internal dining and hessian outside wrapping as above. The connection from Pokfulam Reservoir has not yet been laid.

280. The Upper Pumping Station is connected by means of an 18" internal dia, steel branch main and the slow sand beds at Elliot are connected by a subsidiary 12′′ internal dia. steel main.

Invert Level of Inlet Pipe at Sandy Bay Gap... Invert Level of Tunnel at Sandy Bay Gap...........

O.D. 307.50

Level of 4′-0′′ gauge at Sandy Bay Gap.

Invert of Outlet Pipe at Sandy Bay Gap... Invert of Inlet Pipe to Elliot Rapid Gravity

Filters

306.00

307.00

303.63

297.00

281. Item 8, Pumping Station-Aberdeen Upper Pumping Station. This work was referred to in paragraph 250 Item 8 of last year's Report. A contract for the building of the Pumping Station was let to Messrs. Kin Lee & Co. on 4th May, 1931 for $5,372.95 By the end of August the building contract was finished and by the end of September the installation of the pump and electric motor completed. After successful tests in October the pump was put into operation in pumping out the