P.W.E. Hong Kong.

Q 30

191. Sai Ying Pun, New Market. This work was fully described in paragraph 108 of last year's report. The building proceeded satisfactorily and by the end of the year the carcase was nearing completion and work had been commenced on internal finishings and fittings.

1931 Expenditure... $123,776.57

Expenditure to 31st Dec., 1931...... $137,298.46

192. Latrine and Bathhouse on Praya East.--This work was referred to in paragraph 113 of last year's Report. It was satisfactorily completed on 22nd June, 1931 and handed over to Sanitary Department. At the request of the Sanitary Department the latrine only was constructed.

1931 Expenditure.......... $5,992.10

Expenditure to 31st Dec., 1931.............. $11,322.27

193. Latrine and Urinal at Davis Street (30 seats).—This work was referred to in paragraph 223 of last year's Report. The building was satisfactorily completed on 4th May, 1931,

1931 Expenditure... $4,809.40

Expenditure to 31st Dec., 1931.. $8,695.62

194. Market at Praya East Reclamation.-The work consisted of the erection of a one storey (open type) market constructed of reinforced concrete. The Contract for the work was let to Messrs. Lam Construction Co. for a sum of $26,359.50 on 1st October, 1931. Satisfactory progress was made. Excavation of foundations, piling and concreting of columns were completed by the end of the year.

Expenditure $9,950.47

GENERAL WORKS.

195. Roads.-Consequent upon the erection of new buildings, kerbing and channelling operations were executed on twenty roads, etc., the footpaths being paved and any necessary alterations in levels or alignment being affected.

196. Repairs to the hillside above the Peak Garage were also undertaken.

Expenditure $38,816.72

197. Drainage :-(a) Training Nullahs.-The following is the most important nullah work carried out during the year:

Locality Description of work. Length trained (in feet) Expenditure Remarks. Wong Nei Chong. Western wall of Sing Wo Road Nullah between L.L's. 2660 and 2668 and complete nullah from L.L. 2668 to a point south-east of L.L. 2675 Mui Hing Street, 263' $12,785.73 Completed.

Edit History

2026-05-09 08:23:51 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
P.W.E. Hong Kong. Q 30 191. Sai Ying Pun, New Market. This work was fully described in paragraph 108 of last year's report. The building proceeded satisfactorily and by the end of the year the carcase was nearing completion and work had been commenced on internal finishings and fittings. 1931 Expenditure... $123,776.57 Expenditure to 31st Dec., 1931...... $137,298.46 192. Latrine and Bathhouse on Praya East.--This work was referred to in paragraph 113 of last year's Report. It was satisfactorily completed on 22nd June, 1931 and handed over to Sanitary Department. At the request of the Sanitary Department the latrine only was constructed. 1931 Expenditure.......... $5,992.10 Expenditure to 31st Dec., 1931.............. $11,322.27 193. Latrine and Urinal at Davis Street (30 seats).—This work was referred to in paragraph 223 of last year's Report. The building was satisfactorily completed on 4th May, 1931, 1931 Expenditure... $4,809.40 Expenditure to 31st Dec., 1931.. $8,695.62 194. Market at Praya East Reclamation.-The work consisted of the erection of a one storey (open type) market constructed of reinforced concrete. The Contract for the work was let to Messrs. Lam Construction Co. for a sum of $26,359.50 on 1st October, 1931. Satisfactory progress was made. Excavation of foundations, piling and concreting of columns were completed by the end of the year. Expenditure $9,950.47 GENERAL WORKS. 195. Roads.-Consequent upon the erection of new buildings, kerbing and channelling operations were executed on twenty roads, etc., the footpaths being paved and any necessary alterations in levels or alignment being affected. 196. Repairs to the hillside above the Peak Garage were also undertaken. Expenditure $38,816.72 197. Drainage :-(a) Training Nullahs.-The following is the most important nullah work carried out during the year: Locality Description of work. Length trained (in feet) Expenditure Remarks. Wong Nei Chong. Western wall of Sing Wo Road Nullah between L.L's. 2660 and 2668 and complete nullah from L.L. 2668 to a point south-east of L.L. 2675 Mui Hing Street, 263' $12,785.73 Completed.
Baseline (Original)
P.W.E. Hong Kong. Q 30 191. Sai Ying Pun, New Market.This work was fully described in paragraph 108 of last year's report. The building proceeded satisfactorily and by the end of the year the carcase was nearing completion and work had been commenced on in- ternal finishings and fittings. 1931 Expenditure... $123,776.57 Expenditure to 31st Dec., 1931......$137,298.46 192. Latrine and Bathhouse on Praya East.--This work was referred to in paragraph 113 of last year's Report. It was satisfactorily completed on 22nd June, 1931 and handed over to Sanitary Department. At the request of the Sanitary De- partment the latrine only was constructed. 1931 Expenditure.......... $5,992.10 Expenditure to 31st Dec., 1931.............. $11,322.27 193. Latrine and Urinal at Davis Street (30 seats).—This work was referred to in paragraph 223 of last year's Report. The building was satisfactorily completed on 4th May, 1931, 1931 Expenditure... Expenditure to 31st Dec., 1981.. $4,809.40 $8,695.62 194. Market at Praya East Reclamation.-The work con- sisted of the erection of a one storey (open type) market construct- ed of reinforced concrete. The Contract for the work was let to Messrs. Lam Construction Co. for a sum of $26,359.50 on 1st October, 1981. Satisfactory progress was made. Excavation of foundations, piling and concreting of columns were completed by the end of the year. Expenditure GENERAL WORKS. $9,950.47 195. Roads.-Consequent upon the erection of new buildings, kerbing and channelling operations were executed on twenty roads, etc., the footpaths being paved and any necessary alterations in levels or alignment being affected. 196. Repairs to the hillside above the Peak Garage were also undertaken. Expenditure $38,816.72 197. Drainage :-(a) Training Nullahs.-The following is the most important nullah work carried out during the year:- I ocality Description of work. Wong Nei Western wall of Sing Wo Road Nullah Chong. between L.L's. 2660 and 2668 and complete nullah from 1.L. 2668 to a point south-east of I.L. 2675 Mui Hing Street, Expenditure Length trained Remarks. (in feet) 263' Completed. ļ $12,785.73
2026-05-09 08:23:51 · Baseline
View content

P.W.E. Hong Kong.

Q 30

191. Sai Ying Pun, New Market.This work was fully described in paragraph 108 of last year's report. The building proceeded satisfactorily and by the end of the year the carcase was nearing completion and work had been commenced on in- ternal finishings and fittings.

1931 Expenditure...

$123,776.57

Expenditure to 31st Dec., 1931......$137,298.46

192. Latrine and Bathhouse on Praya East.--This work was referred to in paragraph 113 of last year's Report.

It was satisfactorily completed on 22nd June, 1931 and handed over to Sanitary Department. At the request of the Sanitary De- partment the latrine only was constructed.

1931 Expenditure..........

$5,992.10

Expenditure to 31st Dec., 1931.............. $11,322.27

193. Latrine and Urinal at Davis Street (30 seats).—This work was referred to in paragraph 223 of last year's Report. The building was satisfactorily completed on 4th May, 1931,

1931 Expenditure...

Expenditure to 31st Dec., 1981..

$4,809.40 $8,695.62

194. Market at Praya East Reclamation.-The work con- sisted of the erection of a one storey (open type) market construct- ed of reinforced concrete. The Contract for the work was let to Messrs. Lam Construction Co. for a sum of $26,359.50 on 1st October, 1981. Satisfactory progress was made. Excavation of foundations, piling and concreting of columns were completed by the end of the year.

Expenditure

GENERAL WORKS.

$9,950.47

195. Roads.-Consequent upon the erection of new buildings, kerbing and channelling operations were executed on twenty roads, etc., the footpaths being paved and any necessary alterations in levels or alignment being affected.

196. Repairs to the hillside above the Peak Garage were also undertaken.

Expenditure

$38,816.72

197. Drainage :-(a) Training Nullahs.-The following is the most important nullah work carried out during the year:-

I ocality

Description of work.

Wong Nei Western wall of Sing Wo Road Nullah

Chong.

between L.L's. 2660 and 2668 and complete nullah from 1.L. 2668 to a point south-east of I.L. 2675 Mui Hing Street,

Expenditure

Length

trained

Remarks.

(in feet)

263'

Completed.

ļ

$12,785.73