AnnualReport-1928 — Page 632

Administrative Reports 行政報告書 All AI Reviewed

Q 71

P.W.E. Kowloon.

That section of the work to the South of Argyle Street was completed early in the year. The remainder was not made a part of the contract since cutting from the working face in Argyle Street was used to fill in below the Railway Station.

1928 Estimates, $500.00 Total Estimates, $7,500.00

1928 Expenditure, $499.08

Expenditure up to 31.12.28, $2,998.08

153. Forming level areas in Tai Shek Ku Valley opposite Cemetery. This work was referred to in paragraph 145 of the Report for last year.

The work of filling in the old Indian Cemetery Area, referred to in paragraph 187 on page 90 of last year's report was completed early in the year.

Messrs. Li Hing & Bros. contractors for the above work, also carried out the filling in of the area opposite the Cemetery together with the provision of concrete stanchions and pipe railing for the Indian Cemetery as an extension of the contract.

The work was completed by the end of the year.

Estimates, $12,500.00 Expenditure, $11,779.79

154. Chinese Cemeteries, Laying out new areas.-Work carried out under this head has already been alluded to in paragraph 31 of this report.

Estimates, $16,000.00 Expenditure, $15,844.28

155. Exhumation, Chinese Cemeteries.-Certain exhumation work was carried out for this Department by the Sanitary Department.

1928 Estimates, $20,000.00

Waterworks:---

156. Distributing Water Mains.-The undermentioned mains were laid during the year:

Size of Main Length in feet Locality 4" 170 Portland Street 4" 430 Shantung Street 6" 420 Shek Ku Long Road 6" 1,950 Woo Sung Street 6" 200 Apliu Street 6" 650 Tong Mi Road 8" 1,820 To Kwa Wan Road

Estimates, $10,000.00 Expenditure, $9,834.29

Edit History

2026-05-09 00:34:05 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Q 71 P.W.E. Kowloon. That section of the work to the South of Argyle Street was completed early in the year. The remainder was not made a part of the contract since cutting from the working face in Argyle Street was used to fill in below the Railway Station. 1928 Estimates, $500.00 Total Estimates, $7,500.00 1928 Expenditure, $499.08 Expenditure up to 31.12.28, $2,998.08 153. Forming level areas in Tai Shek Ku Valley opposite Cemetery. This work was referred to in paragraph 145 of the Report for last year. The work of filling in the old Indian Cemetery Area, referred to in paragraph 187 on page 90 of last year's report was completed early in the year. Messrs. Li Hing & Bros. contractors for the above work, also carried out the filling in of the area opposite the Cemetery together with the provision of concrete stanchions and pipe railing for the Indian Cemetery as an extension of the contract. The work was completed by the end of the year. Estimates, $12,500.00 Expenditure, $11,779.79 154. Chinese Cemeteries, Laying out new areas.-Work carried out under this head has already been alluded to in paragraph 31 of this report. Estimates, $16,000.00 Expenditure, $15,844.28 155. Exhumation, Chinese Cemeteries.-Certain exhumation work was carried out for this Department by the Sanitary Department. 1928 Estimates, $20,000.00 Waterworks:--- 156. Distributing Water Mains.-The undermentioned mains were laid during the year: Size of Main Length in feet Locality 4" 170 Portland Street 4" 430 Shantung Street 6" 420 Shek Ku Long Road 6" 1,950 Woo Sung Street 6" 200 Apliu Street 6" 650 Tong Mi Road 8" 1,820 To Kwa Wan Road Estimates, $10,000.00 Expenditure, $9,834.29
Baseline (Original)
Q 71 P.W.E. Kowloon. That section of the work to the South of Argyle Street was completed early in the year. The remainder was not made a part of the contract since cutting from the working face in Argyle Street was used to fill in below the Railway Station. 1928 Estimates, 1928 Expenditure, $500.00 Total Estimates, Expenditure up $499.08 to 31.12.28, $7,500.00 $2,998.08 153. Forming level areas in Tai Shek Ku Valley opposite Cemetery. This work was referred to in paragraph 145 of the Report for last year. The work of filling in the old Indian Cemetery Area, re- ferred to in paragraph 187 on page 90 of last year's report was completed early in the year. Messrs. Li Hing & Bros. contractors for the above work, also carried out the filling in of the area opposite the Cemetery together with the provision of concrete stanchions and pipe rail- ing for the Indian Cemetery as an extension of the contract. The work was completed by the end of the year. Estimates, Expenditure, $12,500.00 $11,779.79 154. Chinese Cemeteries, Laying out new areas.-Work carried out under this head has already been alluded to in para- graph 31 of this report. Estimates, Expenditure, $16,000.00 $15,844.28 155. Exhumation, Chinese Cemeteries.-Certain exhuma- tion work was carried out for this Department by the Sanitary Department. 1928 Estimates, Waterworks:--- 156. Distributing Water $20,000.00 Mains.-The undermentioned mains were laid during the year:- Size of Main. Length in feet. Locality. 4" 170 Portland Street. 4" 430 6" 420 6" 1,950 6" 200 6" 650 8" 1,820 Estimates, Expenditure, Shantung Street. Shek Ku Long Road. Woo Sung Street. Apliu Street. Tong Mi Road. To Kwa Wan Road. $10,000.00 $9,834.29
2026-05-09 00:34:05 · Baseline
View content

Q 71

P.W.E. Kowloon.

That section of the work to the South of Argyle Street was completed early in the year. The remainder was not made a part of the contract since cutting from the working face in Argyle Street was used to fill in below the Railway Station.

1928 Estimates,

1928 Expenditure,

$500.00 Total Estimates,

Expenditure up

$499.08 to 31.12.28,

$7,500.00

$2,998.08

153. Forming level areas in Tai Shek Ku Valley opposite Cemetery. This work was referred to in paragraph 145 of the Report for last year.

The work of filling in the old Indian Cemetery Area, re- ferred to in paragraph 187 on page 90 of last year's report was completed early in the year.

Messrs. Li Hing & Bros. contractors for the above work, also carried out the filling in of the area opposite the Cemetery together with the provision of concrete stanchions and pipe rail- ing for the Indian Cemetery as an extension of the contract.

The work was completed by the end of the year.

Estimates, Expenditure,

$12,500.00 $11,779.79

154. Chinese Cemeteries, Laying out new areas.-Work carried out under this head has already been alluded to in para- graph 31 of this report.

Estimates, Expenditure,

$16,000.00 $15,844.28

155. Exhumation, Chinese Cemeteries.-Certain exhuma- tion work was carried out for this Department by the Sanitary Department.

1928 Estimates,

Waterworks:---

156. Distributing Water

$20,000.00

Mains.-The

undermentioned

mains were laid during the year:-

Size of Main.

Length in feet.

Locality.

4"

170

Portland Street.

4"

430

6"

420

6"

1,950

6"

200

6"

650

8"

1,820

Estimates, Expenditure,

Shantung Street.

Shek Ku Long Road. Woo Sung Street. Apliu Street.

Tong Mi Road.

To Kwa Wan Road.

$10,000.00 $9,834.29