P.W.E. Hong Kong.
Q 60
123. New Workshop and Plant.-The Shaping Machine referred to in paragraph 126 of last year's Report was received and installed.
No further work was undertaken.
1927 Estimates, $3,000.00
Total Estimates, $52,000.00
1927 Expenditure, $2,906.44
Expenditure to 31.12.27, $47,969.28
124. Bowen Road Filter Beds,-Conversion.-This work was referred to in paragraph 130 of last year's Report.
Good progress was made with the construction and erection of the plant, and the filters were set in operation on 27th May.
The works generally consist of six rapid gravity filter beds, each 24 feet by 12 feet, containing the filtering medium composed of 2′ 1′′ of fine graded sand and 1′ 8′′ of specially graded pebbles, and a chemical house containing the machinery and reagent proportioning gear.
On completion of the new filters, the work of converting the two remaining slow sand filter beds into additional service reservoirs was commenced. These beds were cleared of their old filtering medium and covered over with a flat reinforced concrete roof supported on piers of vitrified bricks taken from the original slow sand filter beds. Considerable alteration had to be made to the draw-off wells to meet the new conditions and new 18′′ and 15′′ diameter C.I. mains were laid to the main reservoir and the No. 4 Motor respectively. A satisfactory increase in efficiency of this motor has resulted from the extra head of feed water.
By the end of the year the whole plant had been satisfactorily completed and tested, and all retention monies paid.
1927 Estimates, $50,000.00
Total Estimates, $68,000.00
1927 Sup. Votes, $18,000.00
1927 Expenditure, $66,486.61
Expenditure to 31.12.27, $151,000.00
$144,889.90
125. Tai Tam Tuk Scheme,—Engine and Boiler.-A reference to this work appeared in paragraph 181 of last year's Report. The installation of the new No. 5 Engine was completed and the floor and wall tiles were fixed during the year.
1927 Estimates, $30,000.00
Total Estimates, $281,000.00
1927 Sup. Votes, $95,000.00
$125,000.00
1927 Expenditure, $117,281.86
Expenditure to 31.12.27, $276,056.50
P.W.E. Hong Kong.
Q 60
123. New Workshop and Plant.-The Shaping Machine referred to in paragraph 126 of last year's Report was received and installed.
No further work was undertaken.
1927 Estimates,
1927 Expenditure,
$3,000.00 Total Estimates,
$52,000.00
$2,906.44
Expenditure to 31.12.27,
$47,969.28
124. Bowen Road Filter Beds,-Conversion.-This work was referred to in paragraph 130 of last year's Report.
Good progress was made with the construction and erection of the plant, and the filters were set in operation on 27th May.
The works generally consist of six rapid gravity filter beds, each 24 feet by 12 feet, containing the filtering medium com- posed of 2′ 1′′ of fine graded sand and 1′ 8′′ of specially graded pebbles, and a chemical house containing the machinery and reagent proportioning gear.
On completion of the new filters, the work of converting the two remaining slow sand filter beds into additional service reservoirs was commenced. These beds were cleared of their old filtering medium and covered over with a flat reinforced concrete roof supported on piers of vitrified bricks taken from the original slow sand filter beds. Considerable alteration had to be made to the draw-off wells to meet the new conditions and new 18′′ and 15′′ diameter C.I. mains were laid to the main reservoir and the No. 4 Motor respectively. A satisfactory increase in efficiency of this motor has resulted from the extra head of feed water.
By the end of the year the whole plant had been satisfac- torily completed and tested, and all retention monies paid.
1927 Estimates, 1927 Sup. Votes,
1927 Expenditure,
$50,000.00 Total Estimates, $18,000.00
$68,000.00 Expenditure to $66,486.61
31.12.27,
$151,000.00
$144,889.90
125. Tai Tam Tuk Scheme,—Engine and Boiler.-A refer- ence to this work appeared in paragraph 181 of last year's Report. The installation of the new No. 5 Engine was com- pleted and the floor and wall tiles were fixed during the year.
1927 Estimates,
1927 Sup. Votes,
$30,000.00 Total Estimates, . $281,000.00
95,000.00
$125,000.00 Expenditure to
1927 Expenditure, . $117,281.86
31.12.27,
$276,056.50