EXPENDITURE ON PORT WORKS EXTRAORDINARY.

Estimated. Supplementary Votes. Total. Actual. Unexpended Balance. P.W.E. 1. Ferry Piers... ... 2. Reclamation at Q. B. M. L 200,000 100,000 300,000 300,000.00 Nil. 3. Forming Rubble Mound at North Point... Nil. 35,167.81 35,167.81 35,167.81 Nil. 200,000 100,000 300,000 200,000.00 64,832.19 4. Kennedy Town Reclamation 30,000 30,000 8,988.90 21,011.10 5. Erection of two Tide Gauges 300,000 300,000 300,000.00 Nil. 6. Miscellaneous Works (H'kong ).. 20,000 20,000 2,963.05 17,036.95 7. (a) P. E. R. Contribution by Government 10,000 10,000 9,018.40 981.60 ... 97,000 64,000 161,000 160,115.00 885.00 7. (b) P. E. R. Morrison Hill Development. 13. 8. Filling in tidal Flats at Taikoktsui... ... 40,000 40,000 24,127.48 15,872.52 9. Miscellaneous works (Kowloon)... 150,000 150,000 99,447.24 50,552.76 10. Further Reclamation at Shamshuipo 5,000 5,000 22.53 4,977.47 11. Construction of Water Boat Dock at Laichikok 150,000 ... 150,000 85,221.81 64,775.19 12. Kowloon Bay East Reclamation.. ... 200,000 244,000* 201,365.61 42,634.39 Miscellaneous Works (N.T.) 100,000 10,000 100,000 55,680.52 44,319.48 10,000 10,000 Nil. 10,000.00 Total 1,412,000 108,000 1,520,000 682,121.35 837,878.65

* Sum contributed by the Kailan Mining Administration towards the cost of construction of the West Quay Wall.

Harbour Developments.

Edit History

2026-05-07 11:10:47 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
EXPENDITURE ON PORT WORKS EXTRAORDINARY. Estimated. Supplementary Votes. Total. Actual. Unexpended Balance. P.W.E. 1. Ferry Piers... ... 2. Reclamation at Q. B. M. L 200,000 100,000 300,000 300,000.00 Nil. 3. Forming Rubble Mound at North Point... Nil. 35,167.81 35,167.81 35,167.81 Nil. 200,000 100,000 300,000 200,000.00 64,832.19 4. Kennedy Town Reclamation 30,000 30,000 8,988.90 21,011.10 5. Erection of two Tide Gauges 300,000 300,000 300,000.00 Nil. 6. Miscellaneous Works (H'kong ).. 20,000 20,000 2,963.05 17,036.95 7. (a) P. E. R. Contribution by Government 10,000 10,000 9,018.40 981.60 ... 97,000 64,000 161,000 160,115.00 885.00 7. (b) P. E. R. Morrison Hill Development. 13. 8. Filling in tidal Flats at Taikoktsui... ... 40,000 40,000 24,127.48 15,872.52 9. Miscellaneous works (Kowloon)... 150,000 150,000 99,447.24 50,552.76 10. Further Reclamation at Shamshuipo 5,000 5,000 22.53 4,977.47 11. Construction of Water Boat Dock at Laichikok 150,000 ... 150,000 85,221.81 64,775.19 12. Kowloon Bay East Reclamation.. ... 200,000 244,000* 201,365.61 42,634.39 Miscellaneous Works (N.T.) 100,000 10,000 100,000 55,680.52 44,319.48 10,000 10,000 Nil. 10,000.00 Total 1,412,000 108,000 1,520,000 682,121.35 837,878.65 * Sum contributed by the Kailan Mining Administration towards the cost of construction of the West Quay Wall. Harbour Developments.
Baseline (Original)
EXPENDITURE ON PORT WORKS EXTRAORDINARY. Estimated. Supplement- ary Votes. Total. Actual. Unexpended Balance. P.W.E. 1. Ferry Piers... ... 2. Reclamation at Q. B. M. L 4 3. Forming Rubble Mound at North Point... 200,000 100,000 200,000 100,000 Nil. 35,167.81 200,000.00 64,832.19 ... 30,000 30,000 8,988.90 21,011.10 4. Kennedy Town Reclamation 300,000 300,000 Nil. 300,000,00 5. Erection of two Tide Gauges 20,000 20,000 2,963.05 17,036.95 6. Miscellaneous Works (H'kong ).. 10,000 10,000 9,018.40 981.60 7. (a) P. E. R. Contribution by Government ... 97,000 64,000 161,000 160,115.00 885.00 7. (b) P. E. R. Morrison ITill 13. Development. 8. Filling in tidal Flats at Taikok- tsui... 9. Miscellaneous works (Kowloon)... 10. Further Reclamation at Sham- shuipo 11. Construction of Water Boat Dock at Laichikok 12. Kowloon Bay East Reclamation.. Miscellaneous Works (N.T.) ... 40,000 40,000 24,127.48 15,872.52 150,000 150,000 99,447 24 50,552 76 5,000 5,000 22.53 4,977.47 150,000 ... 150,000 85,221.81 64,775.19 ... 200,000 * 44,000 244,000 201,365.61 42,634.39 100,000 10,000 100,000 10,000 55,680.52 44,319.48 Nil. 10,000.00 1,412,000 108,000 1,520,000 682,121.35 837,878.65 181 * Sum contributed by the Kailan Mining Administration towards the cost of construction of the West Quay Wall. Harbour Developments.
2026-05-07 11:10:47 · Baseline
View content

EXPENDITURE ON PORT WORKS EXTRAORDINARY.

Estimated.

Supplement-

ary Votes.

Total.

Actual.

Unexpended Balance.

P.W.E. 1.

Ferry Piers...

...

2. Reclamation at Q. B. M. L 4 3. Forming Rubble Mound at North

Point...

200,000

100,000

200,000 100,000

Nil. 35,167.81

200,000.00

64,832.19

...

30,000

30,000

8,988.90

21,011.10

4. Kennedy Town Reclamation

300,000

300,000

Nil.

300,000,00

5. Erection of two Tide Gauges

20,000

20,000

2,963.05

17,036.95

6. Miscellaneous Works (H'kong )..

10,000

10,000

9,018.40

981.60

7.

(a) P. E. R. Contribution by

Government

...

97,000

64,000

161,000

160,115.00

885.00

7.

(b) P. E. R. Morrison

ITill

13.

Development.

8. Filling in tidal Flats at Taikok-

tsui...

9. Miscellaneous works (Kowloon)... 10. Further Reclamation at Sham-

shuipo

11. Construction of Water Boat Dock

at Laichikok

12. Kowloon Bay East Reclamation.. Miscellaneous Works (N.T.)

...

40,000

40,000

24,127.48

15,872.52

150,000

150,000

99,447 24

50,552 76

5,000

5,000

22.53

4,977.47

150,000

...

150,000

85,221.81

64,775.19

...

200,000

* 44,000

244,000

201,365.61

42,634.39

100,000

10,000

100,000 10,000

55,680.52 44,319.48

Nil.

10,000.00

1,412,000

108,000

1,520,000

682,121.35

837,878.65

181

* Sum contributed by the Kailan Mining Administration towards the cost of construction of the West Quay Wall.

Harbour Developments.

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.