Q 191
Harbour Developments.
The dredging of the trenches for the rubble mound was completed and the greater portion of the pell-mell rubble deposited.
1924 Estimates, $50,000.00 | Total Estimates, $175,000.00
1924 Sup. Vote, $25,162.01
$76,162.01 Expenditure to 31.12.24,
1921 Expenditure, $75,162.01 | $77,886.10
7. Ferry Piers.-This work was referred to in paragraph 127 of the Report of the Director of Public Works for last year.
With the exception of preliminary surveys made for the purpose of determining the location of the ferry piers on the Hongkong side of the Harbour, no work was undertaken under this vote during the year.
1924 Estimates, $5,000.00 | Total Revised Estimate, $300,000.00
1924 Expenditure, $524.69 | Expenditure to 31.12.24, $161,480.52
8. Ferry Piers for Vehicular Traffic.—This work was referred to in paragraph 128 of the Report of the Director of Public Works for last year.
With the exception of a preliminary survey of the site for the vehicular ferry pier on the Hongkong side of the Harbour, no work was carried out under this vote during the year.
1924 Estimates, $10,000.00 | Total Estimates, $600,000.00
1924 Expenditure, $529.77 | Expenditure to 31.12.24, $560.39
9. Kennedy Town Reclamation.-During the year, the original design of this work was amended and the works will now form part of the Proposed Harbour Development Scheme.
Actual construction had not commenced at the end of the year.
1924 Estimates, $1,000.00 | Total Revised Estimate, $1,626,000.00
1924 Expenditure...
WORKS NOT APPEARING IN ESTIMATES.
10. Quay Wall at M. Ls. 430 & 431, North Point.-During the year, a contract was prepared on behalf of the Ching Siong
Q 191
Harbour Developments.
The dredging of the trenches for the rubble mound was com- pleted and the greater portion of the pell-mell rubble deposited.
1924 Estimates, ..$50,000.00 | Total Estimates,.....$175,000.00 1924 Sup. Vote,...... 25,162.01
$76,162.01 Expenditure to
31.12.24,
1921 Expenditure,...$75,162.01 |
$ 77,886.10
7. Ferry Piers.-This work was referred to in paragraph 127 of the Report of the Director of Public Works for last year.
With the exception of preliminary surveys made for the purpose of determining the location of the ferry piers on the Hongkong side of the Harbour, no work was undertaken under this vote during the year.
1924 Estimates,
$5,000.00
1924 Expenditure,...$ 524.69 |
Total Revised
Estimate, Expenditure to
31.12.24,
$300,000.00
$161,480.52
8. Ferry Piers for Vehicular Traffic. —This work was referred to in paragraph 128 of the Report of the Director of Public Works for last year.
With the exception of a preliminary survey of the site for the vehicular ferry pier on the Hongkong side of the Harbour, no work was carried out under this vote during the year.
1924 Estimates,.
..$10,000.00 | Total Estimates,
Expenditure to
1924 Expenditure,...$ 529.77 31.12.24,
.$600,000.00
$ 560.39
the
the year,
9. Kennedy Town Reclamation.-During the original design of this work was amended and the works will now form part of the Proposed Harbour Development Scheme.
year.
Actual construction had not commenced at the end of the
1924 Estimates, .... $1,000.00 | Total Revised 1924 Expenditure..........
Estimate, ......$ 1,626,000.00
WORKS NOT APPEARING IN ESTIMATES.
10. Quay Wall at M. Ls. 430 & 431, North Point.-During the year, a contract was prepared on behalf of the Ching Siong
No comments yet.
Private notes are available after approval.