AnnualReport-1924 — Page 645

Administrative Reports 行政報告書 All AI Reviewed

P.W.E. Hongkong.

Q 96

(s.) Queen's Road, West, Improvements. It was found impossible to proceed with this work during the year; there was consequently no expenditure under this heading.

1924 Estimates, $1,000.00

1924 Expenditure,

(t.) Stubbs Road, surfacing for heavy traffic.-The sections of the road lying between Bowen Road and Wanchai Gap, and between Barker Road and Gough Hill were regraded, and strengthened with the addition of 4" tar macadam.

1924 Estimates, $20,000.00

1924 Sup. Vote, $100,000.00

$120,000.00

1924 Expenditure, $122,196.61

(u.) Road from Caine Road to Robinson Road.-It was decided not to proceed with this work; there was consequently no expenditure under this heading.

1924 Estimates, $1,000.00

1924 Expenditure,

(v.) Island Road, surfacing for heavy traffic between Aberdeen and Stanley.—This road was strengthened at various places to withstand the increasing vehicular traffic.

1924 Estimates, $100,000.00

1924 Expenditure, $97,184.14

(w.) Caine Road, widening and raising to new levels between Arbuthnot Road and Aberdeen Street.—The property on I.L. 94, between Shelley and Peel Streets, was rebuilt to the new alignment enabling the footpath to be raised to the new levels.

It was impossible to complete this work, as the resumption of certain properties to admit of the widening was not completed.

1924 Estimates, $20,000.00

1924 Expenditure, $4,294.09

Page 645

Page 646

Edit History

2026-05-07 08:04:40 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
P.W.E. Hongkong. Q 96 (s.) Queen's Road, West, Improvements. It was found impossible to proceed with this work during the year; there was consequently no expenditure under this heading. 1924 Estimates, $1,000.00 1924 Expenditure, (t.) Stubbs Road, surfacing for heavy traffic.-The sections of the road lying between Bowen Road and Wanchai Gap, and between Barker Road and Gough Hill were regraded, and strengthened with the addition of 4" tar macadam. 1924 Estimates, $20,000.00 1924 Sup. Vote, $100,000.00 $120,000.00 1924 Expenditure, $122,196.61 (u.) Road from Caine Road to Robinson Road.-It was decided not to proceed with this work; there was consequently no expenditure under this heading. 1924 Estimates, $1,000.00 1924 Expenditure, (v.) Island Road, surfacing for heavy traffic between Aberdeen and Stanley.—This road was strengthened at various places to withstand the increasing vehicular traffic. 1924 Estimates, $100,000.00 1924 Expenditure, $97,184.14 (w.) Caine Road, widening and raising to new levels between Arbuthnot Road and Aberdeen Street.—The property on I.L. 94, between Shelley and Peel Streets, was rebuilt to the new alignment enabling the footpath to be raised to the new levels. It was impossible to complete this work, as the resumption of certain properties to admit of the widening was not completed. 1924 Estimates, $20,000.00 1924 Expenditure, $4,294.09 Page 645 Page 646
Baseline (Original)
P.W.E. Hongkong. Q 96 (s.) Queen's Road, West, Improvements. It was found im- possible to proceed with this work during the year; there was consequently no expenditure under this heading. 1924 Estimates, 1924 Expenditure,...... .$ 1,000.00 (t.) Stubbs Road, surfaring for heavy traffic.-The sections of the road Tying between Bowen Road and Wanchai Gap, and between Barker Road and Gough Hill were regraded, and strengthened with the addition of 4" tar macadam. 1924 Estimates, 1924 Sup. Vote, $ 20,000.00 100,000.00 $ 120,000.00 1924 Expenditure,................... $122,196.61 (u.) Road from Caine Road to Robinson Road.-It was decided not to proceed with this work; there was consequently no expenditure under this heading. 1924 Estimates,..... $ 1,000.00 1924 Expenditure,.............. (v.) Island Road,-- surfacing_for_heavy traffic between Aberdeen and Stanley.—This road was strengthened at various places to withstand the increasing vehicular traffic. 1924 Estimates,... .$ 100,000.00 1924 Expenditure, $ 97,184.14 (w,) Caine Road,-widening and raising to new levels between Arbuthnot Road and Aberdeen Street.—The property on I.L. 94, between Shelley and Peel Streets, was rebuilt to the new aligu- ment enabling the footpath to be raised to the new levels. It was impossible to complete this work, as the resumption of certain properties to admit of the widening was not completed. 1924 Estimates,. 1924 Expenditure, ... $ 20,000.00 $ 4,294.09 Page 645Page 646
2026-05-07 08:04:40 · Baseline
View content

P.W.E. Hongkong.

Q 96

(s.) Queen's Road, West, Improvements. It was found im- possible to proceed with this work during the year; there was consequently no expenditure under this heading.

1924 Estimates,

1924 Expenditure,......

.$ 1,000.00

(t.) Stubbs Road, surfaring for heavy traffic.-The sections of the road Tying between Bowen Road and Wanchai Gap, and between Barker Road and Gough Hill were regraded, and strengthened with the addition of 4" tar macadam.

1924 Estimates, 1924 Sup. Vote,

$ 20,000.00 100,000.00

$ 120,000.00

1924 Expenditure,................... $122,196.61

(u.) Road from Caine Road to Robinson Road.-It was decided not to proceed with this work; there was consequently no expenditure under this heading.

1924 Estimates,.....

$ 1,000.00

1924 Expenditure,..............

(v.) Island Road,-- surfacing_for_heavy traffic between Aberdeen and Stanley.—This road was strengthened at various places to withstand the increasing vehicular traffic.

1924 Estimates,... .$ 100,000.00 1924 Expenditure, $ 97,184.14

(w,) Caine Road,-widening and raising to new levels between Arbuthnot Road and Aberdeen Street.—The property on I.L. 94, between Shelley and Peel Streets, was rebuilt to the new aligu- ment enabling the footpath to be raised to the new levels.

It was impossible to complete this work, as the resumption of certain properties to admit of the widening was not completed.

1924 Estimates,. 1924 Expenditure,

...

$ 20,000.00 $ 4,294.09

Page 645Page 646