P.W.E. Hongkong.
Serious damage was done to the works by heavy typhoon seas. The damage was repaired and the works completed by September.
1923 Estimates, $14,000.00 Total Estimates, $24,000.00
1923 Sup. Vote, $7,000.00 $21,000.00 Expenditure to 31.12.23, $23,638.30 1923 Expenditure, $20,595.04
134. Ap Lei Chau, - Reclamation Scheme. This work was referred to in paragraph 118 of last year's Report.
Provision was made in the 1923 Estimates for drainage works and the formation of roads, but it was not found possible to proceed with this work during the year.
1923 Estimates, $10,000.00 Total Estimates, $43,000.00
1923 Expenditure, $... Expenditure to 31.12.23, $32,713.50
135. Harbour Developments. -- This work was referred to in paragraph 120 of last year's Report.
The Report of the Consulting Engineers (Messrs. Coode, Fitzmaurice, Wilson & Mitchell) on "Hongkong Harbour Improvements" was received in January and published in May, in which latter month it was referred to the Hongkong General Chamber of Commerce for its consideration.
The Consulting Engineers' scheme is confined to the Development of Hunghom Bay, where, it is recommended, six jetties forming Ship and Junk Basins should be ultimately constructed. These jetties are to provide 8,600 lineal feet of berthage for ocean-going steamers and 5,650 lineal feet of berthage for junks and small craft. The depth of water proposed alongside the former is 36 feet below L.W.L.E.S.T. and alongside the latter 15 feet below L.W.L.E.S.T.
The first instalment of the proposed works recommended comprises: -
(a) The construction of two jetties to provide 2,600 lineal feet of ocean-going steamer berthage and 2,050 lineal feet of junk berthage;
(b) 7 acres of Reclamation in connection with the two jetties to provide for railway communication;
(c) Dredging part of Belcher Ridge;
(d) Dredging Cust Rocks.
The cost of these works is estimated at £1,260,000.
P.W.E. Hongkong.
serious damage was
Q 92
done to the works by heavy typhoon seas. The damage was repaired
was repaired and the works completed by
September.
1923 Estimates,
$14,000.00 Total Estimates,
......$24,000.00
·
1923 Sup. Vote,......
7,000.00
$21,000.00 Expenditure to
1923 Expenditure,...$20,595.04 31.12.23,
$23,638.30
134. Aplichau,-Reclamation Scheme. This work was referred
to in paragraph 118 of last year's Report.
Provision was made in the 1923 Estimates for drainage works and the formation of roads, but it was not found possible to proceed with this work during the year.
1923 Estimates, .... 10,000.00 Total Estimates,
......
1923 Expenditure, ...$
$43,000.00
Expenditure, to 31.12.23,
.$32,713.50
135. Ilárbour Developments.--This work was referred to in paragraph 120 of last year's Report.
The Report of the Consulting Engineers (Messrs. Coode, Fitzmaurice, Wilson & Mitchell) on "Hongkong Harbour Improvements" was received in January and published in May, in which latter month it was referred to the Hongkong General Chamber of Commerce for its consideration.
The Consulting Engineers' scheme is confined to the Develop- ment of Hunghom Bay, where, it is recommended, six Jetties forming Ship and Junk Basins should be ultimately constructed. These jetties are to provide 8,600 lineal feet of berthage for ocean-going steamers and 5,650 lineal feet of berthage for junks and small craft. The depth of water proposed alongside the former is 36 feet below L.W.L.E.S.T. and alongside the latter 15 feet below L.W.L.E.S.T.
The first instalment of the proposed works recommended comprises:-
(a.) The construction of two jetties to provide 2,600 lineal feet of ocean-going steamer berthage and 2,050 lineal feet of junk berthage;
(6.) 7 acres of Reclamation in connection with the two jetties to provide for railway communication;
(c.) Dredging part of Belcher Ridge;
(d.) Dredging Cust Rocks.
The cost of these works is estimated at £1,260,000.