Q 48

157. Dredging:-This work was referred to in paragraph 186 of last year's Report. Dredging West of Kowloon Peninsula continued and was completed by May 30th. During the year, 184,872 cube yards of material were dredged by Government. Additional dredging carried out on behalf of the Admiralty and the Hong Kong and Kowloon Wharf & Godown Company is referred to in paragraph 194 under "Works not appearing in Estimates".

Expenditure
Expenditure to 31st Dec., 1935
$161,715.49 $285,292.95

158. Construction of Yard for Storage of Sand at Hung Hom:-A contract for the construction of sand storage bins was let to Messrs. Woo Hing on the 18th March. In all fifty-two bins were built, each bin holding thirty-three cubic yards of sand. The contract was completed satisfactorily in July. Two electric lights in kitchen and quarters were installed.

Expenditure
ELECTRICAL
$13,754.14

159. Tubular Heating System for Operating Theatre, Kowloon Hospital: ---Tubular heaters were installed in Operating Theatre.

Expenditure
$715.60

160. Telephone Cable between Hung Hom Wireless Station and Kowloon City Police Station:-A dry core telephone cable was laid between Hung Hom W/T Station and Kai Tak.

Expenditure
$13,178.68

PUBLIC HEALTH & BUILDINGS ORDINANCE.

161. Compensation and Resumptions:-Resumptions were carried out in connection with street widenings and the development of the district under the approved Town Planning Scheme.

Expenditure
$2,300.00

NEW KOWLOON.

GENERAL WORKS.

162. Roads:-Work completed under this head included the surfacing, kerbing and channelling of new roads, and where required to existing roads. Footpaths were paved with granolithic paving or slabs and the necessary improvements made in front of new buildings erected during the year.

Expenditure
$39,739.71