AIR PORT WIRELESS TELEGRAPH STATION,

240. About 50% of the materials arrived during the latter part of the year and installation work was proceeded with.

Expenditure

$26,513.65

GOVERNMENT HOUSE AND CITY DEVELOPMENT.

241. Approach Road to Government House-A contract for the above work, including a section of viaduct near its junction with Stubbs Road was commenced in November and progress up to the end of the year was satisfactory.

Expenditure

$8,925.00

242. Particulars of matters pertaining to the work of the office of the Crown Lands and Surveys are given in full in the Appendix at the end of this Report.

R. M. HENDERSON,

M.INST.C.E., M.I.MECH.E., M.INST.W.E.,

Director of Public Works.

Hong Kong. 1935.