Q 99

P.W.E. New Kowloon.

189. Widening of Nathan Road Extension Northward to Nanchang Street (junction of New Taipo and Castle Peak Roads). This work was referred to in paragraph 217 of last year's Report.

The work of widening Nathan Road Northwards, embodied in Contract for "Filling in areas at Tong Mi and Kowloon Tong" was completed by the end of June, 1930.

The work of kerbing, channelling and laying macadam to carriageway was completed.

Estimates
Expenditure
$5,600.00
$2,710.81

190. Access Road (15 feet wide) to Christian Chinese Cemetery, Kowloon City.—This work was referred to in paragraph 218 of last year's Report.

A Contract for constructing a road 15 feet wide and about 2,000 feet long to give access to the Christian Chinese Cemetery at Kowloon City, from Prince Edward Road, was let to Mr. Man Gang on 21st August, 1930, for a sum of $6,966.00.

Good progress was made during the year.

Estimates
Expenditure
$7,000.00
$4,100.00

191. Castle Peak Road Widening.—This work was referred to in paragraph 265 of last year's Report.

The completion of Castle Peak Road, on a section from Taipo Road to Wong Uk Village, to its full width, 60 feet wide, was undertaken.

The work was carried out by Messrs. Fu On & Co., as an extension to their Contract for "Filling in Areas North-West of Nanchang Street and West of Taipo Road" referred to in paragraph 202, of this report.

Estimates
Expenditure
$5,000.00
$4,992.56