P.W.E. New Kowloon.

100

192. Castle Peak Road, Section from Cheung Sha Wan to Lai Chi Kok.—The construction of Castle Peak Road, Section from Wong Uk Village to Lai Chi Kok, to a width of 60 feet in accordance with the Town Planning Layout was undertaken, to meet the requirements of a district which is being rapidly developed.

A Contract for this work was let to Messrs. Li Yau & Co. on 9th April, 1930 for a sum of $25,278.50.

Good progress was made during the year. All culverts and the majority of the rubble pitching to slopes were completed. A small section of the road at Wong Uk has been opened to traffic.

Estimates Expenditure

$30,000.00

$18,942.24

193. Improvement to Taipo Road Junction with Castle Peak Road to North of No. 3 Mile Stone.—It was not found possible to undertake the construction of this road, although preliminary survey work was carried out.

Estimates Expenditure

$18,000.00

$5,199.50

194. Improving existing main roads for motor traffic.—Under this heading portions of Prince Edward Road were kerbed, channelled and surfaced with macadam.

Estimates Expenditure

$25,000.00

$22,423.24

195. Kowloon Tong Development—Connection of Stream East Side of Estate to Main Nullah. (Central).—This work was referred to in paragraph 221 of last year's Report.

The laying of storm water drain on the east side of Kowloon Tong nullah opposite Suffolk Road was commenced in January and completed in September so far as possible.

Estimates Expenditure

$6,000.00 $4,497.46

196. Kowloon Tong Development—Connection of Streams East Side of Estate to Main Nullah. (Southern). The laying of stormwater drain along the line of the future east-west Road on each side of Kowloon Tong nullah was commenced in August and completed as far as was possible in October.

Estimates Expenditure

$15,000.00

$3,831.20

Edit History

2026-05-09 06:06:18 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
P.W.E. New Kowloon. 100 192. Castle Peak Road, Section from Cheung Sha Wan to Lai Chi Kok.—The construction of Castle Peak Road, Section from Wong Uk Village to Lai Chi Kok, to a width of 60 feet in accordance with the Town Planning Layout was undertaken, to meet the requirements of a district which is being rapidly developed. A Contract for this work was let to Messrs. Li Yau & Co. on 9th April, 1930 for a sum of $25,278.50. Good progress was made during the year. All culverts and the majority of the rubble pitching to slopes were completed. A small section of the road at Wong Uk has been opened to traffic. Estimates Expenditure $30,000.00 $18,942.24 193. Improvement to Taipo Road Junction with Castle Peak Road to North of No. 3 Mile Stone.—It was not found possible to undertake the construction of this road, although preliminary survey work was carried out. Estimates Expenditure $18,000.00 $5,199.50 194. Improving existing main roads for motor traffic.—Under this heading portions of Prince Edward Road were kerbed, channelled and surfaced with macadam. Estimates Expenditure $25,000.00 $22,423.24 195. Kowloon Tong Development—Connection of Stream East Side of Estate to Main Nullah. (Central).—This work was referred to in paragraph 221 of last year's Report. The laying of storm water drain on the east side of Kowloon Tong nullah opposite Suffolk Road was commenced in January and completed in September so far as possible. Estimates Expenditure $6,000.00 $4,497.46 196. Kowloon Tong Development—Connection of Streams East Side of Estate to Main Nullah. (Southern). The laying of stormwater drain along the line of the future east-west Road on each side of Kowloon Tong nullah was commenced in August and completed as far as was possible in October. Estimates Expenditure $15,000.00 $3,831.20
Baseline (Original)
P.W.E. New Kowloon. 100 192. Castle Peak Road, Section from Cheung Sha Wan to Lai Chi Kok.—The construction of Castle Peak Road, Section from Wong Uk Village to Lai Chi Kok, to a width of 60 feet in accordance to the Town Planning Layout was undertaken, to meet the requirements of a district which is being rapidly developed. A Contract for this work was let to Messrs. Li Yau & Co. on 9th April, 1930 for a sum of $25,278.50. Good progress was made during the year. All culverts and the majority of the rubble pitching to slopes were completed. A small section of the road at Wong Uk has been opened to traffic. Estimates Expenditure $30,000.00 $18,942.24 193. Improvement to Taipo Road Junction with Castle Peak Road to North of No. 3 Mile Stone.—It was not found possible to undertake the construction of this road, although preliminary survey work was carried out. Estimates Expenditure $18,000.00 $5 199.50 194. Improving existing main roads for motor traffic.- Under this heading portions of Prince Edward Road were kerbed, channelled and surfaced with macadam. Estimates Expenditure $25,000.00 $22,423.24 (Central).--This work was 195. Kowloon Tong Development-Connection of Stream East Side of Estate to Main Nullah. referred to in paragraph 221 of last year's Report. The laying of storm water drain on east side of Kowloon Tong nullah opposite Suffolk Road, was commenced in January and completed in September so far as possible. Estimates Expenditure $ 6.000.00 $4.497.46 196. Kowloon Tong Development...Connection of Streams East Side of Estate to Main Nullah. (Southern). The laying of stormwater drain along the line of future east-west Road on each of Kowloon Tong nullah, was commenced in August and completed as far us was possible in October. Estimates Expenditure $15,000.00 $ 3.831.20
2026-05-09 06:06:18 · Baseline
View content

P.W.E. New Kowloon.

100

192. Castle Peak Road, Section from Cheung Sha Wan to Lai Chi Kok.—The construction of Castle Peak Road, Section from Wong Uk Village to Lai Chi Kok, to a width of 60 feet in accordance to the Town Planning Layout was undertaken, to meet the requirements of a district which is being rapidly developed.

A Contract for this work was let to Messrs. Li Yau & Co. on 9th April, 1930 for a sum of $25,278.50.

Good progress was made during the year. All culverts and the majority of the rubble pitching to slopes were completed. A small section of the road at Wong Uk has been opened to traffic.

Estimates Expenditure

$30,000.00

$18,942.24

193. Improvement to Taipo Road Junction with Castle Peak Road to North of No. 3 Mile Stone.—It was not found possible to undertake the construction of this road, although preliminary survey work was carried out.

Estimates Expenditure

$18,000.00

$5 199.50

194. Improving existing main roads for motor traffic.- Under this heading portions of Prince Edward Road were kerbed, channelled and surfaced with macadam.

Estimates Expenditure

$25,000.00

$22,423.24

(Central).--This work was

195. Kowloon Tong Development-Connection of Stream

East Side of Estate to Main Nullah.

referred to in paragraph 221 of last year's Report.

The laying of storm water drain on east side of Kowloon Tong nullah opposite Suffolk Road, was commenced in January and completed in September so far as possible.

Estimates Expenditure

$ 6.000.00 $4.497.46

196. Kowloon Tong Development...Connection of Streams East Side of Estate to Main Nullah. (Southern). The laying of stormwater drain along the line of future east-west Road on each of Kowloon Tong nullah, was commenced in August and completed as far us was possible in October.

Estimates Expenditure

$15,000.00

$ 3.831.20

Comments