P.W.E. Hong Kong.

115. New Architectural Office. This work, referred to in paragraph 112 of last year's Report, was satisfactorily completed and occupied by the Architectural Staff of the Public Works Department during the month of February.

1925 Estimates, $10,000.00 Total Estimates, $80,000.00 1925 Sup. Vote, $38,000.00

$48,000.00 Expenditure to 31.12.25, $96,108.96

1925 Expenditure, $41,619.85

116. Government Civil Hospital,—Extension to Sisters' Quarters.—This work was referred to in paragraph 117 of last year's Report.

The work progressed satisfactorily, except during the period of unsettled labour conditions, and at the end of the year was almost completed, it being anticipated that the building will be ready for occupation early in 1926.

Owing to the impracticability of carrying out alterations to the existing adjoining Quarters until alternative accommodation is available in the new building, it has been necessary to temporarily defer this and the connecting bridge between the old and the new buildings until 1926.

1925 Estimates, $90,000.00 Total Estimates, $95,000.00

1925 Sup. Vote, $5,000.00 Expenditure to 31.12.25, $111,663.04

1925 Expenditure, $83,387.93 $130,000.00

117. Erection of Temporary Barrack Sheds for Police at "Harbour View"—This work was referred to in paragraph 218 of last year's Report.

The work comprised the erection of four sheds of wood, with concrete floors and tiled roofs, together with the necessary site formation and retaining walls, to provide dormitory accommodation for 56 Chinese and 48 Indian Police.

A Contract for the work was let to Messrs. Tat Lee & Co.

The erection of the building was commenced in January and completed in September.

1925 Estimates, $35,000.00 Total Estimates, $45,000.00

1925 Expenditure, $32,221.77 Expenditure to 31.12.25, $32,221.77