By the end of the year, though considerable delay has arisen through non-delivery of bricks, the shell of the Building was nearly completed.
1924 Estimates, $10,600.00
1921 Sup. Vote, $10,000.00
Total Estimates, $20,600.00
Expenditure to 31.12.24, $4,807.91
1924 Expenditure, $4,807.91
163. Monakoktsui, New Market. This work was referred to in paragraph 161 of last year's Report.
Fair progress was made upon the completion of the piling of the foundations, and by the end of the year 1 section was completed and the other well advanced.
1924 Estimates, $21,000.00
1924 Sup. Vote, $2,000.00
Total Estimates, $23,000.00
Expenditure to 31.12.24, $4,200.50
1924 Expenditure, $4,200.50
164. Quarters for Scavenging coolies at Yaumati.-It was not found possible to proceed with this work; there was consequently no expenditure incurred.
1924 Estimates, $5,000.00
Total Estimates, $5,000.00
Expenditure to 31.12.24, ...
1924 Expenditure, ...
165. Trough Closet at Kowloon City.- Resumption negotiations not having been completed, it was not found possible to proceed with this work; consequently no expenditure was incurred under this heading.
1924 Estimates, $10,000.00
Total Estimates, $12,000.00
Expenditure to 31.12.24, ...
1924 Expenditure, ...
166. Additional Cattle Shed, Mataukok.—This work was referred to in paragraph 169 of last year's Report.
On the scheme for the abattoir at Taikoktsui being put forward, it was suggested that this additional shed could with more advantage be provided at Mataukok, consequently there was no expenditure under this heading.
1924 Estimates, $9,000.00
Total Estimates, $10,000.00
1924 Expenditure, ...
Expenditure to 31.12.24, ...