P.W.E. Kowloon.
112
---
PUBLIC WORKS EXTRAORDINARY
KOWLOON.
159. Kowloon Hospital. --This work was referred to in paragraph 160 of last year's Report.
Progress on the preparation of the site was slower than during 1925 owing to rock being encountered and, as a result, the buildings were somewhat delayed, especially the Native Block.
By the end of the year, the Administration and Kitchen Blocks, the Sisters', Medical Officers' and Servants' Quarters were practically completed except the tiling and fittings.
1924 Estimates, $200,000.00 | Total Estimates, $554,000.00
1924 Sup. Vote, $150,000.00 | $350,000.00
1924 Expenditure, $267,180.48
Expenditure to 31.12.24, $438,013.07
160. New Police Station, Yaumati.--Nothing remained to be done during the year, except the settlement of payments due under the contract.
1924 Estimates, $20,000.00 | Total Estimates, $250,000.00
1924 Sup. Vote, $10,000.00 | $30,000.00
Expenditure to 31.12.24, $267,551.05
1924 Expenditure, $28,200.67
161. Police Station, Mongkoktsui.--This work was referred to in paragraph 162 of last year's Report.
The sum included in the Estimates was for the payment of the Retention Money but as payment was effected in December, 1923, there was consequently no expenditure to be recorded.
162. Mutaukok Slaughter House, Inspectors' Quarters.—This work was referred to in paragraph 163 of last year's Report.
These quarters provide a Dining and Living Rooms, with a Pantry, amah's and wash rooms on the ground floor; on the 1st floor there are 3 bed-rooms with 2 bath-rooms. At the rear in a detached building are located the Kitchen and Servants' Quarters.
A contract for the above was let in April to Messrs. Yee Lee & Co.
P.W.E. Kowloon.
112
---
PUBLIC WORKS EXTRAORDINARY
KOWLOON.
159. Kowloon Hospital. --This work was referred to in para- graph 160 of last year's Report.
Progress on the preparation of the site was slower than dur- ing 1925 owing to rock being encountered and, as a result, the buildings were somewhat delayed, especially the Native Block.
By the end of the year, the Administration and Kitchen Blocks, the Sisters', Medical Officers' and Servants' Quarters were prac- tically completed except the tiling and fittings.
1924 Estimates, $200,000.00 | Total Estimates, $554,000.00- 1924 Sup. Vote, -
150,000.00
$350,000.00
1924 Expenditure, $267,180.48
Expenditure to
31.12.24,
$438,013.07
160. New Police Station, Yaumati.-Nothing remained to be
done during the year, except the settlement of payments due under
the contract.
1924 Estimates,.
1924 Sup. Vote,
$20,000.00
Total Estimates, $250,000.00
10,000.00
$30,000.00
Expenditure to
31.12.24,.........$267,551.05-
1924 Expenditure, $28,200.67
161. Police Station, Mongkoktsui.-This work was referred
to in paragraph 162 of last year's Report,
The sum included in the Estimates was for the payment of the Retention Money but as payment was effected in December, 1923, there was consequently no expenditure to be recorded.
162. Mutaukok Slaughter House, Inspectors' Quarters.—This work was referred to in paragraph 163 of last year's Report.
These quarters provide a Dining and Living Rooms, with a Pantry, amah's and wash rooms on the ground floor; on the 1st floor there are 3 bed-rooms with 2 bath-rooms. At the rear in a detached building are located the Kitchen and Servants' Quarters..
A contract for the above was let in April to Messrs. Yee Lee. & Co.
No comments yet.
Private notes are available after approval.