The excavation for the remaining length of 5,000 feet was about two-thirds completed at the close of the year.

1924 Estimates, ...$80,000.00 | Total Estimates, ...$170,000.00

Total Expenditure to 31.12.24,

1924 Expenditure, $76,111.51 | $122,819.05

135. Mount Parker East, Catchwater.—This work was referred to in paragraph 143 of last year's Report.

A commencement was made with the survey for this work, but owing to pressure of other schemes further progress was not possible.

1924 Estimates, ...$50,000.00 | Total Estimates, ...$110,000.00

1924 Expenditure, $96.12 | Total Expenditure, $96.12

136. Violet Hill (only half area), Catchwater.—This work was referred to in paragraph 144 of last year's Report.

After making a detailed inspection of the site during the preliminary survey, it was found that the cost of this work would be rather prohibitive and the scheme has consequently been abandoned.

1924 Estimates, ...$10,000.00 | Total Estimates, ...$95,000.00

1924 Sup. Vote, ...$40,000.00 | $50,000.00*

1924 Expenditure, $561.15 | Total Expenditure to 31.12.24, ...$589.35

* Incorporated with P.W.E. 56.

137. Stanley Mound West, Catchwater.—This work was referred to in paragraph 145 of last year's Report.

By the end of the year, a length of about 3,000 feet of catchwater has been completed to overflow level, and a further length of 2,000 feet excavated to formation level, while the excavation of the remaining part of the Catchwater has reached footpath level. A considerable amount of rock was encountered retarding the progress of the work. During the second half of the year, good progress was made and the work has since been advancing more rapidly.

1924 Estimates, ...$10,000.00 | 1924 Sup. Vote, ...$40,000.00

$50,000.00* |

1924 Expenditure, $14,473.24 | Total Estimates, ...$95,000.00

Total Expenditure, $20,471.77 |

* Incorporated with P.W.E. 55.