P.W.E. New Territories.

struction of two twin culverts, 5′ 0″ x 5' 0", of reinforced concrete.

Land resumptions amounted to $508.79.

1918 Estimates,......$ 20,000.00 | Total Estimates, ...$ 20,000.00

Expenditure to

1918 Expenditure,... 13,184.96 31/12/18,

13,184.96

(f) General Works.-The following is a statement of the works executed under this heading :-

(i.) Shamshuipo Market-Forming to new levels, kerbing, channelling and macadamizing carriageway (half width) on all sides of the market and laying granolithic slabs to footways,..... $ 1,879.37

(ii.) Laichikok Road-Forming, kerbing, channelling and macadamizing carriageway (half width) on the north, south and east sides of N.K.I.L. 26; laying granolithic slabs to footways and paving scavenging lane,

(iii.) Nan Chang Street-Forming, kerbing, channelling and macadamizing carriageway (half width) on the north, south and east sides of N.K.I.L. 21; laying granolithic slabs to footways and paving scavenging lane,

(iv.) Nan Chang Street-Forming, kerbing, channelling and macadamizing carriageway (half width) on the north and east sides N.K.I.L. 17; laying granolithic slabs to footways and paving scavenging lane,

(v.) Ki Lung Street-Forming, kerbing, channelling and macadamizing carriageway (half width) on the south side of N.K.I.L. 43; laying granolithic slabs to footways and paving scavenging lane,

(vi.) Pei Ho Street-Kerbing, channelling and macadamizing carriageway (half width) on the north, south and west sides of N.K.I.L. 158; laying granolithic slabs to footways and paving scavenging lane,

(vii.) Tai Nan Street-Forming, kerbing, channelling and macadamizing carriageway (half width) on the south side of N.K.I.L's 68 and 69; laying granolithic slabs to footway and paving scavenging lane,...

(viii.) Pei Ho Street-Forming, kerbing, channelling and macadamizing carriageway (half width) on the south and west sides of N.K.I.L. 161,

(i)$ 1,879.37 (ii)1,750.53 (iii)1,587.58 (iv)1,064.07 (v)841.98 (vi)803.69 (vii)527.05 (viii)305.84