P.W.E. New Territories,

Q 86

(ix.) Kweilin Street - Forming, kerbing, channelling and macadamizing carriageway (half width) on the south and east sides of N.K.I.L. 155; laying granolithic slabs to footways and paving scavenging lane,... (x.) Tai Nan Street - Forming, kerbing, channelling and macadamizing carriageway (half width) on the north and west sides of N.K.I.L. 19 and laying granolithic slabs to footways, (xi.) Improvement of cross roads at the junction of Castle Peak and Sheung Shui Train Halt Roads,

(xii.) Widening road opposite Un Long Market to 40 feet (not completed),...

$ 394.41
320.28
1,327.31
...
2,791.78

(xiii) Extension towards Sheung Shui for a distance of 1,800 lineal feet of the Frontier Road,

1,307.67

Items (i)-(x). All these items were rendered necessary by the erection of buildings on the various lots mentioned.

Items (xi)-(xiii). These are self-explanatory.

131. Miscellaneous Drainage Works.-The following is a statement of the principal works carried out under this heading during the year :-

(i.) Extension of 6" sewer in road between N.K.I.L's 158 and 23 for N.K.I.L. 161, Shamshuipo, (completed),
Cost of work, $451.11
Less contribution by lessee, 350.00
$101.11

(ii) Extension of 6" sewer in lane north of N.K.I.L's 160, 52 and 58, Shamshuipo, (completed), $847.82

(iii) Extension of 12" storm-water drain in Tai Nan Street from Pei Ho Street to Nan Chang Street, Shamshuipo, (completed), $1,889.86

(iv.) Extension of 12" storm-water drain in Ki Lung Street from Pei Ho Street to Nan Chang Street, Shamshuipo, (completed), $1,792.08

(v.) Extension of 12" storm-water drain in Ya Chau Street from Pei Ho Street to Nan Chang Street, Shamshuipo, (completed), $1,436.76

(vi.) Extension of 12" storm-water drain in Tai Nan Street from Kweilin Street to Yen Chow Street, Shamshuipo, (completed), $1,665.83

(vii.) Extension of 12" storm-water drain in Ki Lung Street from Kweilin Street to Yen Chow Street, Shamshuipo, (completed), $1,690.12

Edit History

2026-05-06 19:17:06 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
P.W.E. New Territories, Q 86 (ix.) Kweilin Street - Forming, kerbing, channelling and macadamizing carriageway (half width) on the south and east sides of N.K.I.L. 155; laying granolithic slabs to footways and paving scavenging lane,... (x.) Tai Nan Street - Forming, kerbing, channelling and macadamizing carriageway (half width) on the north and west sides of N.K.I.L. 19 and laying granolithic slabs to footways, (xi.) Improvement of cross roads at the junction of Castle Peak and Sheung Shui Train Halt Roads, (xii.) Widening road opposite Un Long Market to 40 feet (not completed),... $ 394.41 320.28 1,327.31 ... 2,791.78 (xiii) Extension towards Sheung Shui for a distance of 1,800 lineal feet of the Frontier Road, 1,307.67 Items (i)-(x). All these items were rendered necessary by the erection of buildings on the various lots mentioned. Items (xi)-(xiii). These are self-explanatory. 131. Miscellaneous Drainage Works.-The following is a statement of the principal works carried out under this heading during the year :- (i.) Extension of 6" sewer in road between N.K.I.L's 158 and 23 for N.K.I.L. 161, Shamshuipo, (completed), Cost of work, $451.11 Less contribution by lessee, 350.00 $101.11 (ii) Extension of 6" sewer in lane north of N.K.I.L's 160, 52 and 58, Shamshuipo, (completed), $847.82 (iii) Extension of 12" storm-water drain in Tai Nan Street from Pei Ho Street to Nan Chang Street, Shamshuipo, (completed), $1,889.86 (iv.) Extension of 12" storm-water drain in Ki Lung Street from Pei Ho Street to Nan Chang Street, Shamshuipo, (completed), $1,792.08 (v.) Extension of 12" storm-water drain in Ya Chau Street from Pei Ho Street to Nan Chang Street, Shamshuipo, (completed), $1,436.76 (vi.) Extension of 12" storm-water drain in Tai Nan Street from Kweilin Street to Yen Chow Street, Shamshuipo, (completed), $1,665.83 (vii.) Extension of 12" storm-water drain in Ki Lung Street from Kweilin Street to Yen Chow Street, Shamshuipo, (completed), $1,690.12
Baseline (Original)
" P.W.E. New Territories, Q 86 (ix.) Kweilin Street-Forming, kerbing, channel- ling and macadamizing carriageway (half width) on the south and east sides of N.K.I.L. 155; laying granolithic slabs to footways and paving scavenging lane,... (x.) Tai Nan Street-Forming, kerbing, channel- ling and macadamizing carriageway (half width) on the north and west sides of N.K.I. L. 19 and laying granolithic slabs to footways, (xi.) Improvement of cross roads at the junction of Castle Peak and Sheung Shui Train Halt Roads, (xii.) Widening road opposite Ün Long Market to 40 feet (not completed),... $ 394.41 320.28 1.327.31 ... 2.791.78 (xiii) Extension towards Sheung Shui for a distance of 1,800 lineal feet of the Frontier Road, 1,307.67 Items (i)-(x). All these items were rendered necessary by the erection of buildings on the various lots mentioned. Items (xi)-(xiii). These are self-explanatory. 131. Miscellaneous Drainage Works.-The following is a statement of the principal works carried out under this heading during the year :- (i.) Extension of 6" sewer in road between N.K. I.L's 158 and 23 for N.K.I.L. 161, Sham- shuipo, (completed), iii Cost of work, Less contribution by lessee, $451.11 350.00 101.11 847.82 (ii) Extension of 6" sewer in lane north of N.K. 1.L's 160,52 and 58, Shamshuipo, (completed), Extension of 12" storm-water drain' in Tai Nan Street from Pei Ho Street to Nan Chang Street, Shamshuipo, (completed), (iv.) Extension of 12" storm-water drain in Ki Lung Street from Pei Ho Street to Nan Chang Street, Shamshuipo, (completed), (v.) Extension of 12" storin-water drain in Ya Chau Street from Pei Ho Street to Nan Chang Street, Shamshuipo, (completed), (vi.) Extension of 12" storm-water drain in Tai Nan Street from Kweilin Street to Yen Chow Street, Shamshuipo, (completed), (vii.) Extension of 12" storm-water, drain in Ki Lung Street from Kweilin Street to Yen Chow Street, Shamshuipo, (completed), 1,889.86 1,792.08 1,436.76 1,665.83 1.690.12
2026-05-06 19:17:06 · Baseline
View content

"

P.W.E. New Territories,

Q 86

(ix.) Kweilin Street-Forming, kerbing, channel- ling and macadamizing carriageway (half width) on the south and east sides of N.K.I.L. 155; laying granolithic slabs to footways and paving scavenging lane,... (x.) Tai Nan Street-Forming, kerbing, channel- ling and macadamizing carriageway (half width) on the north and west sides of N.K.I. L. 19 and laying granolithic slabs to footways, (xi.) Improvement of cross roads at the junction of Castle Peak and Sheung Shui Train Halt Roads,

(xii.) Widening road opposite Ün Long Market to

40 feet (not completed),...

$ 394.41

320.28

1.327.31

...

2.791.78

(xiii) Extension towards Sheung Shui for a distance

of 1,800 lineal feet of the Frontier Road,

1,307.67

Items (i)-(x). All these items were rendered necessary by the erection of buildings on the various lots mentioned.

Items (xi)-(xiii). These are self-explanatory.

131. Miscellaneous Drainage Works.-The following is a statement of the principal works carried out under this heading during the year :-

(i.) Extension of 6" sewer in road between N.K. I.L's 158 and 23 for N.K.I.L. 161, Sham-

shuipo, (completed),

iii

Cost of work,

Less contribution by lessee,

$451.11 350.00

101.11

847.82

(ii) Extension of 6" sewer in lane north of N.K. 1.L's 160,52 and 58, Shamshuipo, (completed), Extension of 12" storm-water drain' in Tai Nan Street from Pei Ho Street to Nan Chang Street, Shamshuipo, (completed),

(iv.) Extension of 12" storm-water drain in Ki Lung Street from Pei Ho Street to Nan Chang Street, Shamshuipo, (completed), (v.) Extension of 12" storin-water drain in Ya Chau Street from Pei Ho Street to Nan Chang Street, Shamshuipo, (completed), (vi.) Extension of 12" storm-water drain in Tai Nan Street from Kweilin Street to Yen Chow Street, Shamshuipo, (completed), (vii.) Extension of 12" storm-water, drain in Ki Lung Street from Kweilin Street to Yen Chow Street, Shamshuipo, (completed),

1,889.86

1,792.08

1,436.76

1,665.83

1.690.12